This section includes 63 Mcqs, each offering curated multiple-choice questions to sharpen your Software Engg knowledge and support exam preparation. Choose a topic below to get started.
1. |
In the critical path of construction planning, free float can be |
A. | Greater than the total float |
B. | Less than the total float |
C. | Greater than the independent float |
D. | Less than the independent float |
Answer» D. Less than the independent float | |
2. |
Quality circles in the construction industry can have the following participants |
A. | Engineers and architects |
B. | Contractors and raw materials suppliers |
C. | Clients and consultants |
D. | All of the above |
Answer» E. | |
3. |
Independent float is an amount of time by which the start of an activity may be delayed without affecting1. the preceding or the following activity2. the start of a following activity3. the completion of the project |
A. | 1 only |
B. | 2 only |
C. | 3 only |
D. | 1, 2 and 3 |
Answer» E. | |
4. |
In PERT, how much probability is considered for expected activity duration? |
A. | 33% |
B. | 50% |
C. | 67% |
D. | 99% |
Answer» C. 67% | |
5. |
A scaled drawing of the proposed construction site showing all the relevant features such as entry and exit points to the site, storage area for materials, toilets, workers quarters, etc. is called |
A. | Construction Plan |
B. | Job Layout |
C. | Development Plan |
D. | Architectural Plan |
Answer» C. Development Plan | |
6. |
In PERT analysis of a project having large number of activities in its critical path, which of the following assumption is correct? |
A. | Both activity durations and project completion time follow β- distribution |
B. | Both activity durations and project completion time follow normal distribution |
C. | Activity durations follow normal distribution, but project completion time follows β- distribution |
D. | Activity durations follow β - distribution, but project completion time follows normal distribution |
Answer» E. | |
7. |
Activities A, B, C and D constitute a small project; their interrelationship, expected duration and standard deviation of this expected duration are shown in the figure, respectively. With a view to improving the speed of implementation, each of B, C and D are split into three equal segments, maintaining appropriate inter-relationships between A and each of these nine segments. What will be the standard deviation of the modified project duration after segmentation (to the nearest \(\frac{1}{{10}}\) unit)? |
A. | 6.2 |
B. | 5.6 |
C. | 5.2 |
D. | 4.6 |
Answer» B. 5.6 | |
8. |
A float (or slack) in a critical path method (CPM) is amount of time that a task can be delayed without causing any delay to |
A. | Subsequent tasks and project completion date |
B. | Interdependent tasks |
C. | Subsequent tasks only |
D. | Preceding tasks |
E. | Project completion date only |
Answer» B. Interdependent tasks | |
9. |
In PERT analysis, the time estimates of activities follow |
A. | normal distribution curve |
B. | β -distribution curve |
C. | Poisson’s distribution curve |
D. | binomial distribution curve |
Answer» C. Poisson’s distribution curve | |
10. |
Mile stone chart is an improvement over |
A. | Bar chart |
B. | CPM Scheduling |
C. | PERT scheduling |
D. | OPST scheduling |
Answer» B. CPM Scheduling | |
11. |
In Network Analysis the commencement or completion of an activity is called |
A. | Time |
B. | Duration |
C. | Event |
D. | Period |
Answer» D. Period | |
12. |
Independent float of an activity (i, j) is denoted by IF (i, j). The earliest occurrence times of i and j are denoted by Ei and Ej respectively. The latest occurrence times of i and j are denoted by Li and Lj respectively. D (i, j) indicates the duration of the activity. |
A. | Ej – Li - D (i, j) |
B. | Lj – Ei - D (i, j) |
C. | Lj – Ej - D (i, j) |
D. | Ej - Ei |
Answer» B. Lj – Ei - D (i, j) | |
13. |
In PERT, the time estimates of activities are probabilistic and the probability of their occurrence follows |
A. | Binomial distribution |
B. | β - distribution |
C. | Normal distribution |
D. | Poisson’s distribution |
Answer» C. Normal distribution | |
14. |
If D is the duration, ES and EF are the earliest start time and earliest finish time, LS and LF are the latest start time and latest finish time, then the following relation(s) hold(s) good :A. EF = ES + DB. LS = LF – DC. D = EF – ESSelect the code for the correct answer from the options given below : |
A. | A and C only |
B. | A and B only |
C. | C only |
D. | A,B,C |
Answer» E. | |
15. |
A _______ is similar to an activity but it does not consume any resources. |
A. | Dummy |
B. | Event |
C. | Slack |
D. | None of the above |
Answer» B. Event | |
16. |
Contractor X is developing his bidding strategy against Contractor Y. The ratio of Y's bid price to X's cost for the 30 previous bids in which Contractor X has competed against Contractor Y is given in the TableRation of Y’s bid Price of X’s costNumber of bids1.0261.04121.0631.1061.123 Based on the bidding behaviour of the Contractor Y, the probability of winning against Contractor Y at a mark up of 8% for the next project is |
A. | 100% |
B. | 0% |
C. | more than 50% but less than 100% |
D. | more than 0% but less than 50% |
Answer» E. | |
17. |
In project network analysis, which of the following statements is TRUE? |
A. | All critical activities must join two critical events |
B. | All activities joining two critical events are necessarily critical |
C. | Some activities having non-zero floats can be critical |
D. | Dummy activities can never become critical |
Answer» B. All activities joining two critical events are necessarily critical | |
18. |
ABC analysis is referred to as |
A. | Always Better Control analysis |
B. | Alphabetical Backup Crane analysis |
C. | Analytical Boost Crane analysis |
D. | None of the above |
Answer» B. Alphabetical Backup Crane analysis | |
19. |
It is estimated that an activity can be assigned an optimistic duration of 16 days, a pessimistic duration of 28 days and a most likely duration of 19 days. What is the expected duration for this activity? |
A. | 20 days |
B. | 19 days |
C. | 22 days |
D. | 18 days |
Answer» B. 19 days | |
20. |
In PERT network analysis, the critical path is defined as |
A. | a path with sum of duration of all activities having positive slack values. |
B. | a path with smallest sum of duration of activities on it. |
C. | a path with nodes having positive slack values. |
D. | a path with nodes having zero slack values. |
Answer» E. | |
21. |
Consider the following rules of the network diagram and state which of them are correct:(i) Network always has a single initial and final event.(ii) An event can occur twice.(iii) No activity can start until its tail end event has occurred.(iv) It is usual practice to show time flow from right to left. |
A. | (i), (ii) and (iii) |
B. | (i) and (iii) |
C. | (i), (iii) and (iv) |
D. | (i), (ii), (iii) and (iv) |
Answer» C. (i), (iii) and (iv) | |
22. |
In a bar chart the vertical axis represents |
A. | Time |
B. | Types of activities |
C. | Number of labors |
D. | Various activities of the project |
Answer» E. | |
23. |
Consider the following activity for the total project:ActivityImmediate PredecessorsDuration (DaysA-10B-9CA9DA8EB7FB11GD, E5 The total project duration for the critical path will be |
A. | 25 days |
B. | 23 days |
C. | 21 days |
D. | 19 days |
Answer» C. 21 days | |
24. |
In a CPM network latest finish time for an event I is 8 weeks. Activity I-J takes 4 weeks for completion.Event J starts after 12 weeks. Float for activity I-J is |
A. | 4 weeks |
B. | 8 weeks |
C. | 12 weeks |
D. | 0 weeks |
Answer» E. | |
25. |
In an activity, if the latest start time is 28 days & the earliest start time is 18 days then the total float shall be |
A. | 46 days |
B. | 10 days |
C. | 14 days |
D. | 9 days |
Answer» C. 14 days | |
26. |
A part of quality management system, that indicates the degree to which design quality is achieved in the actual construction work is called: |
A. | Quality of assurance |
B. | Quality of design |
C. | Quality of conformance |
D. | Quality of performance |
Answer» D. Quality of performance | |
27. |
Consider the following assembly with different operations :OperationStandard time, minutesA60B65C29D37E28F63G36H126K64 There are 250 working days in a year to produce 4000 units in a year. The minimum number of work stations required will be |
A. | 13 |
B. | 12 |
C. | 11 |
D. | 10 |
Answer» B. 12 | |
28. |
List the following processes in their correct sequence, from earliest to latest, in project implementation planning:1. Project duration2. Resource histogram3. Standardized input/ performance for each activity including alternatives4. WBS5. Resource optimization considering constraints6. Activities and their inter-relationshipsSelect the correct answer using the code given below. |
A. | 2, 1, 3, 5, 6 and 4 |
B. | 2, 6, 3, 5, 1 and 4 |
C. | 4, 1, 3, 5, 6 and 2 |
D. | 4, 6, 3, 5, 1 and 2 |
Answer» E. | |
29. |
A dummy activity is one which |
A. | Requires time but no other resources |
B. | Requires machinery but no time |
C. | Requires neither time nor any other resources |
D. | Requires people, but not the time |
E. | Requires people and time, but no money |
Answer» D. Requires people, but not the time | |
30. |
In an Activity-on-Arrow network, which of the following rules of network logic are mandatory?1. Any two events can be directly connected by not more than one activity.2. Event numbers should not be duplicated in a network.3. Before an activity may begin, all the activities preceding it must be completed.Select the correct answer using the code given below. |
A. | 1 and 2 only |
B. | 2 and 3 only |
C. | 1 and 3 only |
D. | 1, 2 and 3 |
Answer» E. | |
31. |
A bar chart is drawn for |
A. | time versus activity |
B. | activity versus resources |
C. | resources versus progress |
D. | progress versus time |
Answer» B. activity versus resources | |
32. |
In PERT, If To and Tp are optimistic time and pessimistic time which an activity takes for its performance, then assumed standard deviation to measure uncertainty is taken as |
A. | (To + Tp)/6 |
B. | (4To + 2Tp)/6 |
C. | (2To + 4Tp)/6 |
D. | (Tp – To)/6 |
Answer» E. | |
33. |
Bar charts are considered to be suitable for |
A. | minor works |
B. | major works |
C. | dam constructions |
D. | large projects |
Answer» B. major works | |
34. |
Activity A, Activity B and Activity C are cast into a ladder diagrammatic CPM network, with splitting each into three equal parts as A1, A2, A3 and B1, B2, B3; and C1, C2, C3 Typical sequencing as in a ladder diagram is adopted (like B2 following A2 and B1). The optimum number of dummy arrows needed for a satisfactory and correct ladder diagram will be |
A. | 1 |
B. | 2 |
C. | 3 |
D. | 4 |
Answer» C. 3 | |
35. |
Consider the following statement associated with critical path:1. Critical path is the most important sequence of activities which has no float and which determine the project completion period2. Critical path is the largest path with shortest duration within which the project can be completed3. The difference between early start time and late finish time must be equal to the activity duration4. Cannot pass through dummy activityWhich is among the above are correct statements? |
A. | 1, 2 and 4 |
B. | 1, 3 and 4 |
C. | 1, 2 and 3 |
D. | 1, 2, 3 and 4 |
Answer» D. 1, 2, 3 and 4 | |
36. |
If an activity has its optimistic, most likely and pessimistic times as 2, 4 and 9 respectively, then its expected time and variance are ____ and ______ respectively? |
A. | 4.5 and 7/6 |
B. | 7 and 49/36 |
C. | 4.5 and 49/36 |
D. | 7 and 7/6 |
Answer» D. 7 and 7/6 | |
37. |
In Construction Management, the Critical Path Network helps an engineer |
A. | To concentrate his attention on critical activities |
B. | To divert the resources from non-critical advanced activities to critical activities |
C. | To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project |
D. | All of the above |
Answer» E. | |
38. |
Duration along the critical path defines which of the following? A. Shortest duration needed B. Shortest duration permissible C. Longest duration needed D. Longest duration permissible Select the code for the correct answer from the options given below: |
A. | A and B only |
B. | A and D only |
C. | B and C only |
D. | C and D only |
Answer» C. B and C only | |
39. |
Free float can be associated with which of the following?1. In one of two sub-paths between any two adjacent nodes2. In the last activity in the sub-paths, less by at least one of the sub-paths, between any two nodes3. Following all sub-activities in a laddered network4. Whenever mandatory calendar dates are prescribed for major milestone eventsSelect the correct answer using the code given below. |
A. | 1, 2 and 3 |
B. | 1, 3 and 4 |
C. | 2, 3 and 4 |
D. | 1, 2 and 4 |
Answer» E. | |
40. |
If to, tp and tm are the optimistic, pessimistic, and most likely time estimates of activity respectively, the expected time t of the activity will be |
A. | (to+3tm+tp)/2 |
B. | (to+3tm+tp)/3 |
C. | (to+4tm+tp)/4 |
D. | (to+4tm+tp)/5 |
E. | (to+4tm+tp)/6 |
Answer» F. | |
41. |
A dummy activity in a project network does not consume |
A. | Time |
B. | Material |
C. | Money |
D. | All the above |
Answer» E. | |
42. |
If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the anticipated time of completion of the project with 99.9% probability is |
A. | 16 days |
B. | 12 days |
C. | 10 days |
D. | 6 days |
Answer» B. 12 days | |
43. |
In a CPM network latest finish time for an event i is 10 weeks. Activity i - j takes 4 weeks for Completion . Event J starts after 16 weeks. Total Float for activity i - j is |
A. | 6 weeks |
B. | 12 weeks |
C. | 10 weeks |
D. | 2 weeks |
Answer» E. | |
44. |
CPM in project management stands for: |
A. | Critical Path Method |
B. | Construction Planning & Management |
C. | Control Project Management |
D. | Construction Project Manpower |
Answer» B. Construction Planning & Management | |
45. |
Gantt charts indicate |
A. | Comparison of actual progress with the scheduled progress |
B. | Balance of work to be done |
C. | Progressive cost of project |
D. | Inventory costs |
Answer» B. Balance of work to be done | |
46. |
Gantt chart provides information about |
A. | Breakeven point analysis |
B. | Production schedule |
C. | Material handling layout |
D. | Determining selling price |
Answer» C. Material handling layout | |
47. |
Corporate Social Responsibility (CSR) means? |
A. | Complications of social life |
B. | Compliance of social and ecological responsibility of the companies or organizations |
C. | Corporate life having social responsibilities |
D. | Corporate life having all social responsibilities to be followed |
Answer» C. Corporate life having social responsibilities | |
48. |
If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, then the expected time ‘t’ of the activity will be: |
A. | \(\frac{{{t_o} + {t_p} + {t_m}}}{3}\) |
B. | \({{{t_o} + {t_p} + 3{t_m}}}{5}\) |
C. | \(\frac{{{t_o} + {t_p} + 2{t_m}}}{4}\) |
D. | \(\frac{{{t_o} + {t_p} + 4{t_m}}}{6}\) |
Answer» E. | |
49. |
Fulkerson’s rule is connected with the |
A. | numbering of event in PERT/CPM |
B. | creation of a parallel activity |
C. | queueing theory |
D. | elimination of dummy activity |
Answer» B. creation of a parallel activity | |
50. |
Critical Path is always |
A. | the longest path |
B. | the shortest path |
C. | the most profitable path |
D. | the fastest path |
Answer» B. the shortest path | |