In a CPM network latest finish time for an event I is 8 weeks. Activity I-J takes 4 weeks for completion.Event J starts after 12 weeks. Float for activity I-J is

A. 4 weeks
B. 8 weeks
C. 12 weeks
D. 0 weeks
Answer» E.