Explore topic-wise MCQs in Software Engg.

This section includes 63 Mcqs, each offering curated multiple-choice questions to sharpen your Software Engg knowledge and support exam preparation. Choose a topic below to get started.

51.

A construction company has an annual demand of 200 M / T. of steel, The annual cost of carrying per M. T. of steel is Es. 2000 and the cost of place an order is Rs. 50000. What is the economic order quantity?

A. 50 M.T
B. 70.7 M.T
C. 100 M.T
D. 40 M.T
Answer» D. 40 M.T
52.

Certain key events in the life of a project are called:

A. Dummies
B. Critical events
C. Nodes
D. Milestones
Answer» E.
53.

If the optimistic time, most likely time and pessimistic time or activity A are 4, 6 and 8 weeks. Respectively and for activity B are 5, 5.5 and 9 weeks respectively, then

A. Expected time of activity A is greater than the expected time of activity B
B. Expected time of activity B is greater than the expected time of activity A
C. Expected time of both activities A and B are same
D. Data too inadequate to compute expected times of activities
Answer» D. Data too inadequate to compute expected times of activities
54.

SOFTWARE_PROJECT_ESTIMATION_CAN_NEVER_BE_AN_EXACT_SCIENCE,_BUT_A_COMBINATION_OF_GOOD_HISTORICAL_DATA_AND_SYSTEMATIC_TECHNIQUES_CAN_IMPROVE_ESTIMATION_ACCURACY.?$

A. True
B. False
Answer» B. False
55.

Which of the following is not achieved by an automated estimation tools?

A. Predicting staffing levels
B. Predicting software cost
C. Predicting software schedules
D. Predicting clients demands
Answer» E.
56.

What can be used to complement decomposition techniques and offer a potentially valuable estimation approach in their own right?

A. Automated estimation tools
B. Empirical estimation models
C. Decomposition techniques
D. Both Automated estimation tools and Empirical estimation models
Answer» C. Decomposition techniques
57.

Which of the following is not an option to achieve reliable cost and effort estimate?

A. Base estimates on similar projects that have already been completed
B. Use one or more empirical models for software cost and effort estimation
C. Use relatively simple decomposition techniques to generate project cost and effort estimates
D. The ability to translate the size estimate into human effort, calendar time, and dollars
Answer» E.
58.

The environment that supports the software project is called

A. CLSS
B. SEE
C. FAST
D. CBSE
Answer» C. FAST
59.

The project planner examines the statement of scope and extracts all important software functions which is known as

A. Association
B. Decomposition
C. Planning process
D. All of the mentioned
Answer» C. Planning process
60.

CLSS stands for

A. conveyor line sorting system
B. conveyor line sorting software
C. conveyor line sorting speed
D. conveyor line sorting specification
Answer» B. conveyor line sorting software
61.

A number of independent investigators have developed a team-oriented approach to requirements gathering that can be applied to establish the scope of a project called

A. JAD
B. CLASS
C. FAST
D. None of the mentioned
Answer» D. None of the mentioned
62.

What describes the data and control to be processed?

A. Planning process
B. Software scope
C. External hardware
D. Project complexity
Answer» C. External hardware
63.

Which of the following is an important factor that can affect the accuracy and efficacy of estimates?

A. Project size
B. Planning process
C. Project complexity
D. Degree of structural uncertainty
Answer» B. Planning process