List the following processes in their correct sequence, from earliest to latest, in project implementation planning:1. Project duration2. Resource histogram3. Standardized input/ performance for each activity including alternatives4. WBS5. Resource optimization considering constraints6. Activities and their inter-relationshipsSelect the correct answer using the code given below.

A. 2, 1, 3, 5, 6 and 4
B. 2, 6, 3, 5, 1 and 4
C. 4, 1, 3, 5, 6 and 2
D. 4, 6, 3, 5, 1 and 2