

MCQOPTIONS
Saved Bookmarks
1. |
If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, then the expected time ‘t’ of the activity will be: |
A. | \(\frac{{{t_o} + {t_p} + {t_m}}}{3}\) |
B. | \({{{t_o} + {t_p} + 3{t_m}}}{5}\) |
C. | \(\frac{{{t_o} + {t_p} + 2{t_m}}}{4}\) |
D. | \(\frac{{{t_o} + {t_p} + 4{t_m}}}{6}\) |
Answer» E. | |