Activities A, B, C and D constitute a small project; their interrelationship, expected duration and standard deviation of this expected duration are shown in the figure, respectively. With a view to improving the speed of implementation, each of B, C and D are split into three equal segments, maintaining appropriate inter-relationships between A and each of these nine segments. What will be the standard deviation of the modified project duration after segmentation (to the nearest \(\frac{1}{{10}}\) unit)? |
A. | 6.2 |
B. | 5.6 |
C. | 5.2 |
D. | 4.6 |
Answer» B. 5.6 | |