1.

In a CPM network latest finish time for an event i is 10 weeks. Activity i - j takes 4 weeks for Completion . Event J starts after 16 weeks. Total Float for activity i - j is

A. 6 weeks
B. 12 weeks
C. 10 weeks
D. 2 weeks
Answer» E.