In a CPM network latest finish time for an event i is 10 weeks. Activity i - j takes 4 weeks for Completion . Event J starts after 16 weeks. Total Float for activity i - j is |
A. | 6 weeks |
B. | 12 weeks |
C. | 10 weeks |
D. | 2 weeks |