1.

In PERT, If To and Tp are optimistic time and pessimistic time which an activity takes for its performance, then assumed standard deviation to measure uncertainty is taken as

A. (To + Tp)/6
B. (4To + 2Tp)/6
C. (2To + 4Tp)/6
D. (Tp – To)/6
Answer» E.


Discussion

No Comment Found