In PERT analysis of a project having large number of activities in its critical path, which of the following assumption is correct?

A. Both activity durations and project completion time follow β- distribution
B. Both activity durations and project completion time follow normal distribution
C. Activity durations follow normal distribution, but project completion time follows β- distribution
D. Activity durations follow β - distribution, but project completion time follows normal distribution
Answer» E.