In PERT analysis of a project having large number of activities in its critical path, which of the following assumption is correct? |
A. | Both activity durations and project completion time follow β- distribution |
B. | Both activity durations and project completion time follow normal distribution |
C. | Activity durations follow normal distribution, but project completion time follows β- distribution |
D. | Activity durations follow β - distribution, but project completion time follows normal distribution |
Answer» E. | |