Consider the following assembly with different operations :OperationStandard time, minutesA60B65C29D37E28F63G36H126K64 There are 250 working days in a year to produce 4000 units in a year. The minimum number of work stations required will be |
A. | 13 |
B. | 12 |
C. | 11 |
D. | 10 |
Answer» B. 12 | |