If to, tp and tm are the optimistic, pessimistic, and most likely time estimates of activity respectively, the expected time t of the activity will be |
A. | (to+3tm+tp)/2 |
B. | (to+3tm+tp)/3 |
C. | (to+4tm+tp)/4 |
D. | (to+4tm+tp)/5 |
E. | (to+4tm+tp)/6 |
Answer» F. | |