1.

If to, tp and tm are the optimistic, pessimistic, and most likely time estimates of activity respectively, the expected time t of the activity will be

A. (to+3tm+tp)/2
B. (to+3tm+tp)/3
C. (to+4tm+tp)/4
D. (to+4tm+tp)/5
E. (to+4tm+tp)/6
Answer» F.