It is estimated that an activity can be assigned an optimistic duration of 16 days, a pessimistic duration of 28 days and a most likely duration of 19 days. What is the expected duration for this activity?

A. 20 days
B. 19 days
C. 22 days
D. 18 days
Answer» B. 19 days