A float (or slack) in a critical path method (CPM) is amount of time that a task can be delayed without causing any delay to |
A. | Subsequent tasks and project completion date |
B. | Interdependent tasks |
C. | Subsequent tasks only |
D. | Preceding tasks |
E. | Project completion date only |
Answer» B. Interdependent tasks | |