

MCQOPTIONS
Saved Bookmarks
1. |
If an activity has its optimistic, most likely and pessimistic times as 2, 4 and 9 respectively, then its expected time and variance are ____ and ______ respectively? |
A. | 4.5 and 7/6 |
B. | 7 and 49/36 |
C. | 4.5 and 49/36 |
D. | 7 and 7/6 |
Answer» D. 7 and 7/6 | |