1.

If an activity has its optimistic, most likely and pessimistic times as 2, 4 and 9 respectively, then its expected time and variance are ____ and ______ respectively?

A. 4.5 and 7/6
B. 7 and 49/36
C. 4.5 and 49/36
D. 7 and 7/6
Answer» D. 7 and 7/6