MCQOPTIONS
Saved Bookmarks
1. |
Consider the following activity for the total project:ActivityImmediate PredecessorsDuration (DaysA-10B-9CA9DA8EB7FB11GD, E5 The total project duration for the critical path will be |
A. | 25 days |
B. | 23 days |
C. | 21 days |
D. | 19 days |
Answer» C. 21 days | |