In project network analysis, which of the following statements is TRUE?

A. All critical activities must join two critical events
B. All activities joining two critical events are necessarily critical
C. Some activities having non-zero floats can be critical
D. Dummy activities can never become critical
Answer» B. All activities joining two critical events are necessarily critical