1. |
In project network analysis, which of the following statements is TRUE? |
A. | All critical activities must join two critical events |
B. | All activities joining two critical events are necessarily critical |
C. | Some activities having non-zero floats can be critical |
D. | Dummy activities can never become critical |
Answer» B. All activities joining two critical events are necessarily critical | |