Explore topic-wise MCQs in Bachelor of Business Administration (BBA).

This section includes 83 Mcqs, each offering curated multiple-choice questions to sharpen your Bachelor of Business Administration (BBA) knowledge and support exam preparation. Choose a topic below to get started.

1.

Following are the characteristics of Project Mindset.

A. Time, Responsiveness, Information sharing, Processes, structured planning
B. Time, Project management, Information sharing, Processes, structured planning
C. Time, Responsiveness, Information sharing, capability, structured planning
D. Time, Responsiveness, Information sharing, Processes, project planning
Answer» B. Time, Project management, Information sharing, Processes, structured planning
2.

A program is usually a group of

A. plans
B. people and work
C. related projects
D. unrelated projects
Answer» D. unrelated projects
3.

QC is typically a(n) _______________ process.

A. Management
B. Project manager
C. Audit
D. Inspection
Answer» E.
4.

Traditionally Indian Business had shortage of inputs like Power, Foreign Exchange, Important Raw Material, Supply of Agricultural Raw materials etc.

A. True
B. False
C. none
D. none
Answer» B. False
5.

Cash Flow Statement does not fully reveal the soundness or otherwise of the financial position of the business.

A. True
B. False
C. none
D. none
Answer» B. False
6.

Which of the below financial statements is static and shows the state of Assets and Liabilities on a particular date?

A. Cash Flow Statement
B. Funds Flow Statement
C. Profit and Loss Statement
D. None of the Above
Answer» E.
7.

Industrial Reconstruction Bank of India was established with which specific objective from the below?

A. To assist the rehabilitation of Sick Units
B. To assist the Government
C. To assist construction projects.
D. None of the Above
Answer» B. To assist the Government
8.

In the initial stage of the project the probability of completing the project is ___ .

A. Zero
B. High
C. Low
D. Any of the above
Answer» D. Any of the above
9.

The probability of completing the project can be estimated based upon the ____ .

A. Uniform distribution curve
B. Normal distribution curve.
C. U-shaped distribution curve
D. None of the above
Answer» C. U-shaped distribution curve
10.

Resorce requirement in project becomes constant while the project is in its _____ progress stage.

A. 40 to 55%
B. 55 to 70%
C. 70 to 80%
D. 80 to 95%
Answer» E.
11.

A ____________ is a temporary endeavor undertaken to create a unique product service or result.

A. Assignment
B. Product
C. Research
D. Project
Answer» E.
12.

Each component of the software product is separately estimated and the results aggregated to produce an estimate for the overall job.

A. Algorithmic model
B. Expert judgment
C. Bottom-up
D. Top down
Answer» D. Top down
13.

Which of the following is NOT a project management cause of failed projects?

A. shortcuts taken during the project
B. lack of or imprecise targets
C. inadequate systems analysis and design tools
D. budget overruns
Answer» D. budget overruns
14.

Which of the following is NOT a part of project management?

A. initiating
B. monitoring
C. closing
D. All above are parts
Answer» E.
15.

For a Market Research only Census Survey is done and no Sample Survey is necessary.

A. True
B. False
C. none
D. none
Answer» C. none
16.

The statistical tool that depicts a project s tasks and the relationships between those tasks is known as

A. milestone
B. goal
C. Gantt chart
D. PERT chart
Answer» E.
17.

A horizontal bar chart that shows project tasks against a calendar is called

A. milestone
B. goal
C. Gantt chart
D. PERT chart
Answer» D. PERT chart
18.

The business case and the justification for the project is determined during the _____ phase.

A. initiation
B. planning
C. execution
D. closure
Answer» B. planning
19.

Following are the phases of Project Management Life Cycle. Arrange them in correct order Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing and delivery

A. 3-2-1-4
B. 1-2-3-4
C. 2-3-1-4
D. 4-3-2-1
Answer» B. 1-2-3-4
20.

The scope of the work is defined in which phase of the project management?

A. Initiating
B. Planning
C. Executing
D. Closing
Answer» B. Planning
21.

You have just completed Qualitative Risk Analysis of the project. What should you be doing next?

A. Plan Risk Management
B. Perform Quantitative Risk Analysis
C. Plan Risk Responses
D. Control Risks
Answer» C. Plan Risk Responses
22.

Who are project team members primarily accountable to?

A. External stakeholders.
B. The end users.
C. The finance director.
D. The project manager.
Answer» E.
23.

A process that involves continuously improving and detailing a plan as more detail become available is termed as

A. project analysis
B. project enhancing
C. progressive deliberation
D. progressive elaboration
Answer» E.
24.

Which from the following statement(s) is/are NOT true?I. Projects have defined objectivesII. Programs have a larger scope than projectsIII. The projects and programs in a portfolio must be directly related

A. I only
B. II only
C. III only
D. II and III only
Answer» D. II and III only
25.

Which of the following is responsible for the quality of the project deliverables?

A. The project champion
B. The project team
C. Stakeholders
D. Customers
Answer» C. Stakeholders
26.

Who owns the Project Management Plan (PMP)?

A. The project team.
B. The chief executive.
C. The project manager.
D. The project support office.
Answer» D. The project support office.
27.

Following is (are) the component(s) of risk management

A. Risk Assessment
B. Risk Control
C. Risk Ranking
D. All of the above
Answer» E.
28.

Which from the following represents the correct project cycle?

A. Planning Initiating Executing Closing
B. Planning Executing Initiating Closing
C. Initiating Planning Executing Closing
D. Initiating Executing Planning Closing
Answer» D. Initiating Executing Planning Closing
29.

In Cash Flows, when a firm invests in fixed assets and short-term financial investments it results in

A. Increased Equity
B. Increased Liability
C. Decreased Cash
D. Increased Cash
Answer» D. Increased Cash
30.

While calculating cost of imported machinery, which of the below needs to be considered?

A. FOB Value
B. Shipping, Freight and Insurance Cost
C. Import Duty
D. All of the Above
Answer» E.
31.

Which of the following is regarded as a fundamental flaw in the whole concept of benchmarking?

A. It limits improvements to currently accepted methods of operating.
B. It does not involve learning.
C. It limits critical thinking.
D. It is not a continuous process.
Answer» B. It does not involve learning.
32.

________focuses on developing change -tolerance software.

A. Rapid application development
B. Lean Development
C. Extreme rogramming
D. Spriral
Answer» B. Lean Development
33.

Which one of the following is not a characteristic of a Project?

A. Temporary nature
B. Familiarity
C. Risk
D. Uniqueness
Answer» C. Risk
34.

Which of the following is an example of internal failure cost?

A. Rework
B. Quality audits
C. Random quality audits
D. Project team training
Answer» B. Quality audits
35.

Who has ultimate responsibility for project risk?

A. Steering group.
B. Risk owner.
C. Project sponsor.
D. Project manager.
Answer» D. Project manager.
36.

.If any one factor of a project changes, _____ other factor(s) is/are likely to be affected.

A. all
B. one
C. at least one
D. at most one
Answer» D. at most one
37.

Which one of the following is a constituent of working capital requirement? Raw material and components

A. Debtor
B. Operating expense
C. Both a and b
D. None of the Above
Answer» D. None of the Above
38.

In quality management, which of the following is not an attribute of the cost of nonconformance?

A. Loss of customers
B. Downtime
C. Safety measures
D. Rework
Answer» D. Rework
39.

Optimal quality is reached at what point?

A. When the stakeholder accepts the project deliverable
B. When revenue from improvements equal the costs of conformance
C. When revenue from improvement equals the incremental costs to achieve the quality
D. When revenue from corrective actions equals the costs of the improvement
Answer» D. When revenue from corrective actions equals the costs of the improvement
40.

Business Value =

A. Tangible Elements
B. Intangible Elements
C. Tangible Elements Intangible Elements
D. Tangible Elements + Intangible Elements
Answer» E.
41.

Relationship based on unrelated level of activity and past data of cost is measured with help of

A. cost estimation
B. price estimation
C. unit estimation
D. production estimation
Answer» B. price estimation
42.

Devising and maintaining a workable scheme to accomplish the business need is

A. Initiating process
B. Planning process
C. Executing process
D. Controlling process
Answer» C. Executing process
43.

The structure of a project will vary depending on the _________to provide.

A. benefits it is intended
B. Structure
C. Schedule
D. Assignment
Answer» B. Structure
44.

Which one of the following is not an attribute of a project?

A. Definite starting date
B. Has no definite end date
C. Creates a product, service, or result
D. Requires resources
Answer» C. Creates a product, service, or result
45.

Which one of the following best describes a project issue?

A. A major problem that requires formal escalation.
B. A problem that the project manager has to deal with on a day-to-day basis.
C. An uncertain event that may or may not occur.
D. An opportunity that occurs through change control.
Answer» B. A problem that the project manager has to deal with on a day-to-day basis.
46.

Which of the following is incorrect activity for the configuration management of a software system?

A. Internship management
B. Change management
C. Version management
D. System management
Answer» B. Change management
47.

_________comprehensive and flexible system for achieving, sustaining and maximizing business success

A. Statistical Sampling
B. Six sigma 9s quality
C. Six Sigma
D. Risk
Answer» D. Risk
48.

Once letter of sanction is issued, the borrower has to submit____________ after appropriate board resolution to avail the loan.

A. Copy of the Board Meeting Minutes
B. Letter of Advances
C. Letter of Acceptance
D. Letter of Credit
Answer» D. Letter of Credit
49.

How can organisational structures that are characterised by democratic and inclusive styles of management be described?

A. Hierarchical
B. Bureaucratic
C. Flat
D. Functional
Answer» D. Functional
50.

Which from the following is NOT a tangible element?

A. Fixtures
B. Trademarks
C. Monetary assets
D. Stockholder equity
Answer» C. Monetary assets