Explore topic-wise MCQs in Bachelor of Business Administration (BBA).

This section includes 176 Mcqs, each offering curated multiple-choice questions to sharpen your Bachelor of Business Administration (BBA) knowledge and support exam preparation. Choose a topic below to get started.

1.

The organization as part of its monitoring and control policy may have a ________in place which dictates that certain statistics have to be collected at various stages of aproject.

A. measurement programme.
B. system programme.
C. software programme.
D. testing programme.
Answer» B. system programme.
2.

________ is needed to ensure that the project remains under control and that it continues to meet its business justification.

A. yellow tape.
B. white tape.
C. red tape.
D. black tape.
Answer» D. black tape.
3.

________ is some thing that is described by a set of attributes (data items) and that will be manipulated within the software (system).

A. instance.
B. class.
C. object.
D. data.
Answer» D. data.
4.

A _________ contains a set of attributes that act as an aspect, quality, characteristic, or descriptor of the object.

A. ordinary object.
B. data object.
C. template.
D. instance.
Answer» C. template.
5.

_______ refers to the ability of the software to interact with other systems.

A. interoperability.
B. reliability.
C. functionality.
D. efficiency.
Answer» B. reliability.
6.

_______ is a qualitative measure of the degree to which classes are connected to one another.

A. cohesion.
B. coupling.
C. control.
D. coordination.
Answer» C. control.
7.

A ________ specification is concerned with how much is to spent on the system.

A. functional.
B. quality.
C. resource.
D. scope.
Answer» D. scope.
8.

A ________ specification is concerned with how well the functions are to operate.

A. functional.
B. quality.
C. resource.
D. scope.
Answer» C. resource.
9.

In _________ stage, the entry, exit and process requirements are identified for each activity.

A. review and publicize plan.
B. identify project scope and objectives.
C. analyse project.
D. identify the products and activities of the project.
Answer» E.
10.

The problems experienced in the survey of managers published by Thayer, Pyster and Wood include_________.

A. poor estimates and plans.
B. poor role definition.
C. poor quality control.
D. both a and b.
Answer» E.
11.

When a customer does not identify a detailed input, processing or output requirements, _______ model is used.

A. prototyping.
B. rad.
C. incremental.
D. spiral.
Answer» B. rad.
12.

..is called if subsequent have the time by which an activity may be delayed without affecting.

A. action float.
B. terminal float.
C. free float
D. null float
Answer» D. null float
13.

Zero duration activities but are assumed to start at the same time as the first and the end at the same time as the last one is called__________ activity.

A. hijacked.
B. heuristic.
C. hammocked.
D. hole.
Answer» D. hole.
14.

_________ activities on the network diagram have zero duration and use no resources.

A. dangling.
B. dummy.
C. null.
D. zero.
Answer» C. null.
15.

____ is carried out to calculate the earliest dates on which each activity may be started and completed.

A. backward pass.
B. forward pass.
C. no pass.
D. increasing pass.
Answer» C. no pass.
16.

The activities have zero duration but are assumed to start at the sametime as the first and the end at the same time as the last one iscalled__________ activity.

A. hijacked.
B. heuristic.
C. hammocked.
D. hole.
Answer» D. hole.
17.

________ a set of attributes (data items) and that will be manipulated within the software (system).

A. instance.
B. class.
C. object.
D. data.
Answer» D. data.
18.

__________ relates to the physical resources used when the software is executed.

A. functionality.
B. maintainability.
C. reliability.
D. efficiency.
Answer» E.
19.

Which type of risk factor is most likely to cause problems for a software project developing commercial software?

A. inadequate user documentation.
B. litigation expense.
C. low productivity.
D. cancellation of project.
Answer» B. litigation expense.
20.

_________ indicates the connectedness of the system that can be derived mechanically.

A. dependency.
B. re-occurrence.
C. inheritance
D. relationship.
Answer» E.
21.

The time by which an activity may be delayed without affecting any subsequent activity is called _________.

A. action float.
B. terminal float.
C. free float
D. null float
Answer» D. null float
22.

The objective of ________ is to avoid or minimize the adverse effects of unforeseen events.

A. risk management.
B. risk maintenance.
C. risk taking.
D. risky job.
Answer» B. risk maintenance.
23.

Which form of software development model is most suited to a systemwhere all the requirements are known at the start of a project and remainstable throughout the project?

A. waterfall model.
B. incremental model.
C. evolutionary model.
D. spiral model.
Answer» B. incremental model.
24.

__________ relates to the ability of the software to be transferred to a different environment.

A. portability.
B. maintainability.
C. reliability.
D. efficiency.
Answer» B. maintainability.
25.

Ensuring that all the loose ends of a project are tied up is called as ___________.

A. demanding.
B. decomposing.
C. determining.
D. decommissioning.
Answer» E.
26.

The percentage of a particular time interval that a system is usable is called _____.

A. time interval.
B. availability.
C. utility.
D. mean time.
Answer» C. utility.
27.

"Each activity has been scheduled to start at its earliest start date" is called as_________.

A. likelihood.
B. activity schedule.
C. probability.
D. planning.
Answer» B. activity schedule.
28.

The shortest time in which we could expect to complete the activity, barring outright miracles are called ________.

A. optimistic time.
B. pessimistic time.
C. most likely time.
D. shortest time.
Answer» B. pessimistic time.
29.

In Software Prototype, ___________ means copies of input screens are shown to the users on a workstation, but the screens cannot actually be used.

A. simulation.
B. annealing.
C. mock-ups.
D. rad system.
Answer» D. rad system.
30.

The inspection is led by ________, who has had specific training in the technique.

A. an evaluator.
B. a testing professional.
C. a moderator.
D. a reader.
Answer» D. a reader.
31.

An Elaboration of Waterfall which stresses the necessity for validation activities is known as __________.

A. extended waterfall.
B. iterative model.
C. v-process model.
D. spiral model.
Answer» D. spiral model.
32.

_______ is a working model of one or more aspects of the projected system.

A. evolutionary model.
B. v-process model.
C. spiral model.
D. software prototyping.
Answer» E.
33.

Ranking of the risks and determining risk aversion strategies is called ________.

A. risk analysis.
B. risk control.
C. risk identification
D. risk evaluation.
Answer» E.
34.

_______ is an activity bar chart indicating scheduled activity dates and durations frequently augmented with activity floats.

A. bar chart.
B. ball chart.
C. slip chart.
D. gantt chart.
Answer» B. ball chart.
35.

Ranking of the risks and determining risk aversion strategies is called _______.

A. risk analysis.
B. risk control.
C. risk identification.
D. risk evaluation.
Answer» E.
36.

The priorities we might apply in deciding levels in monitoring is called as ______.

A. hierarchical monitoring.
B. prioritized monitoring.
C. tracking.
D. tracing
Answer» C. tracking.
37.

The activities have zero duration but are assumed to start at the same timeas the first and the end at the same time as the last one is called__________activity.

A. hijacked.
B. heuristic.
C. hammocked.
D. hole.
Answer» D. hole.
38.

_________ activities on the network diagram have zero duration and use no resources.

A. dangling.
B. dummy.
C. null.
D. zero.
Answer» C. null.
39.

The statement "Putting more people on a late job makes it later" is from _________ law.

A. brooks.
B. peters.
C. parkinson s.
D. brokers.
Answer» B. peters.
40.

In _________, the priority activities are allocated resources in ascending order of total. float.

A. total free.
B. total float.
C. technical float.
D. top float.
Answer» C. technical float.
41.

. The scope of the deliverables for an increment is rigidly constrained by an agreed deadline called as ____________.

A. sand boxing.
B. time boxing.
C. time delaying.
D. local delaying.
Answer» C. time delaying.
42.

PERT is _________.

A. process evaluation and review technique.
B. product evaluation and review technique.
C. program evaluation and review technique.
D. project evaluation and review technique.
Answer» D. project evaluation and review technique.
43.

_______ refers to the ability of the software to interact with othersystems.

A. interoperability.
B. reliability.
C. functionality.
D. efficiency.
Answer» B. reliability.
44.

_________ is a technique particularly associated with quality circles.

A. quality plans.
B. fire- fighting.
C. quality checking.
D. brain storming.
Answer» E.
45.

_______ is classified into Functional and Non-functional.

A. project.
B. requirements.
C. start date. .
D. risk
Answer» C. start date. .
46.

The priorities we might apply in deciding levels in monitoring is called as______.

A. hierarchical monitoring.
B. prioritized monitoring.
C. tracking.
D. tracing
Answer» C. tracking.
47.

Which form of software development model is most suited to a systemwhere all the requirements are known at the start of a project and remainstable throughout the project?

A. waterfall model.
B. incremental model.
C. evolutionary model.
D. spiral model.
Answer» B. incremental model.
48.

CMM is acronym of __________.

A. capability maturity model.
B. calculative maturity model.
C. collaborative maturity model.
D. continuous maturity model.
Answer» B. calculative maturity model.
49.

The inspection is led by ________, who has had specific training in thetechnique.

A. an evaluator.
B. a testing professional.
C. a moderator.
D. a reader.
Answer» D. a reader.
50.

__________ relates to the ability of the software to be transferred to adifferent environment.

A. portability.
B. maintainability.
C. reliability.
D. efficiency.
Answer» B. maintainability.