1.

Optimal quality is reached at what point?

A. When the stakeholder accepts the project deliverable
B. When revenue from improvements equal the costs of conformance
C. When revenue from improvement equals the incremental costs to achieve the quality
D. When revenue from corrective actions equals the costs of the improvement
Answer» D. When revenue from corrective actions equals the costs of the improvement