You have just completed Qualitative Risk Analysis of the project. What should you be doing next? |
A. | Plan Risk Management |
B. | Perform Quantitative Risk Analysis |
C. | Plan Risk Responses |
D. | Control Risks |
Answer» C. Plan Risk Responses | |