Which from the following represents the correct project cycle?

A. Planning Initiating Executing Closing
B. Planning Executing Initiating Closing
C. Initiating Planning Executing Closing
D. Initiating Executing Planning Closing
Answer» D. Initiating Executing Planning Closing