Explore topic-wise MCQs in Bachelor of Business Administration (BBA).

This section includes 53 Mcqs, each offering curated multiple-choice questions to sharpen your Bachelor of Business Administration (BBA) knowledge and support exam preparation. Choose a topic below to get started.

1.

. Theory is an important operations research technique to analyze the queuing behaviour.

A. waiting line
B. net work
C. decision
D. simulation
Answer» B. net work
2.

. helps management to evaluate alternative course of action for selecting the best course of action

A. operations research
B. quantitative technique
C. management research
D. none of the above
Answer» B. quantitative technique
3.

.. is an important Operations research technique to be used for determining optimal allocation of limited resources to meet the given objectives.

A. waiting line theory
B. net work analysis
C. decision analysis
D. linear programming
Answer» E.
4.

Who defined Operations Research as scientific approach to problem solving for executive management.

A. E L Arnoff
B. H M Wagner
C. Churchman
D. None of these
Answer» C. Churchman
5.

Operations Research emphasises on the overall approach to the system. This characteristic of Operations Research is often referred to as .................................

A. System orientation
B. System approach
C. Inter-disciplinary
D. Team approach
Answer» E.
6.

............................ models involve the allocation of resources to activities in such a way that some measure of effectiveness is optimised.

A. Sequencing
B. Allocation
C. Queuing theory
D. Decision theory
Answer» C. Queuing theory
7.

The word .................. may be defined as some actions that we apply to some problems or hypothesis.

A. Research
B. Operations
C. Both a and b
D. None of these
Answer» C. Both a and b
8.

........................ models assume that the values of the variables do not change with time during a particular period.

A. Dynamic
B. Static
C. Both a and b
D. None of these
Answer» C. Both a and b
9.

........................may be defined as a method of determining an optimal program of interdependent activities in view of available resources.

A. Goal programming
B. Linear programming
C. Decision making
D. None of these
Answer» C. Decision making
10.

The solution to a transportation problem with m rows and n columns is feasible if the number of positive allocations are:

A. m + n
B. m x n
C. m +n 1
D. m +n + 1
Answer» D. m +n + 1
11.

Graphic method can be applied to solve a liner programming problem when there are only ........................... variables

A. A one
B. Two
C. Three
D. More than three
Answer» C. Three
12.

A minimisation problem can be connected into maximisation problem by changing the signs of coefficients in the ...........................

A. Constraints
B. Objectives
C. Both a and b
D. None of these
Answer» C. Both a and b
13.

In maximisation cases, ....................... are assigned to the artificial variables as their coefficients in the objective function.

A. + m
B. m
C. 0
D. None of these
Answer» B. m
14.

In simplex method, ........................ should be selected when there is tie between slack/surplus variable and decision variable.

A. Slack variable
B. Decision variable
C. Surplus variable
D. None of these
Answer» C. Surplus variable
15.

When at least one of the basic variables is zero, then the basic feasible solution to a Linear Programming Problem is said to be ..............................

A. Infeasible
B. Unbounded
C. Degenerate
D. Non-degenerate
Answer» D. Non-degenerate
16.

Every Linear Programming Problem is related to another Linear Programming Problem, called ..........................

A. Primal
B. Dual
C. Non-linear Programming
D. None of these
Answer» C. Non-linear Programming
17.

In an LPP, if the solution of a variable can be made infinitely large without violating the constraints, then the solution is ..............................

A. Infeasible
B. Alternative
C. Unbounded
D. Unique
Answer» D. Unique
18.

Operations Research does not give perfect solution to a problem, but it helps to improve the ......................... of the solution.

A. Quality
B. Clarity
C. Look
D. None of these
Answer» B. Clarity
19.

Operations Research makes a ...................... attack on complex problems to arrive at optimal solution.

A. Scientific
B. Systematic
C. Both a and b
D. None of these
Answer» D. None of these
20.

......................... deals with making sound decisions under conditions of certainty, risk and uncertainty.

A. Game theory
B. Network analysis
C. Decision theory
D. None of these
Answer» D. None of these
21.

When total supply is equal to total demand in a transportation problem , the problem is said to be

A. balanced
B. unbalanced
C. degenerate
D. none of the above
Answer» B. unbalanced
22.

The initial solution of a transportation problem can be obtained by applying any known method. But the only condition is

A. the solution be optimal
B. the rim conditions are satisfied
C. the solution not be degenerate
D. all of the above
Answer» C. the solution not be degenerate
23.

By the beginning of ........................., the industries in USA realised the importance of Management Science in solving business and management problems.

A. 1930s
B. 1940s
C. 1950s
D. 1960s
Answer» D. 1960s
24.

. is the latest time by which an activity can be started without delaying the completion of the project.

A. est
B. eft
C. lst
D. lft
Answer» D. lft
25.

is the duration by which an activity can be delayed without delaying the project

A. slack
B. total float
C. free float
D. independent float
Answer» C. free float
26.

.is the latest time by which an activity can be finished without delaying the completion of the project.

A. est
B. eft
C. lst
D. lft
Answer» E.
27.

is the time by which the completion of an activity can be delayed beyond its earliest finish time without affecting the earliest start time of a succeeding activity

A. slack
B. total float
C. free float
D. independent float
Answer» D. independent float
28.

An activity which must be completed before one or more other activities start is known as activity.

A. dummy
B. predecessor
C. successor
D. none of these
Answer» C. successor
29.

.is the disconnection of an activity before the completion of activities in a project network diagram.

A. dangling
B. looping
C. dummy
D. none of the above
Answer» D. none of the above
30.

is the shortest possible time in which an activity can be delayed without delaying the project.

A. pessimistic time estimate
B. optimistic time estimate
C. most likely time estimate
D. none of these
Answer» C. most likely time estimate
31.

is the duration by which an activity can be delayed without delaying the project.

A. total float
B. slack
C. earliest event time
D. none of these
Answer» B. slack
32.

If a decision theory problem has 3 decision alternatives and 4 states of nature, the number of payoffs in that problem will be

A. 3
B. 4
C. 12
D. 64
Answer» D. 64
33.

For decision making under uncertainty, identify the decision rule that is appropriate for the optimist.

A. laplace
B. maximax
C. minimax regret
D. maxmin
Answer» C. minimax regret
34.

In a decision theory problem under complete uncertainty, which one of the following approaches will not be possible?

A. expected monetary value
B. maxmin
C. minimax
D. hurwicz
Answer» B. maxmin
35.

While plotting constraints on a graph paper, terminal points on both axes are connected by a straight line because

A. the resources are limited in supply
B. the objective function is a linear function
C. the constraints are linear equations or in equalities
D. all of the above
Answer» D. all of the above
36.

In linear programming problem if all constraints are less than or equal to, then the feasible region is

A. above lines
B. below the lines
C. unbounded
D. none of the above
Answer» C. unbounded
37.

...................... is a method of analysing the current movement of the some variable in an effort to predict the future movement of the same variable.

A. Goal programming
B. Queuing theory
C. Markov Analysis
D. Replacement theory
Answer» D. Replacement theory
38.

An activity which must be completed before commencement of one or more other activities is called.................................

A. Successor activity
B. Predecessor activity
C. Dummy activity
D. None of these
Answer» C. Dummy activity
39.

Activities that cannot be started until one or more of the other activities are completed, are called..........................................

A. Dummy activities
B. Initial activities
C. Successor activities
D. Predecessor activities
Answer» D. Predecessor activities
40.

..................... is the duration by which an activity can be delayed without delaying the completion of the project.

A. Earliest Start Time
B. Earliest Finish Time
C. Latest Start Time
D. Latest Finish Time
Answer» D. Latest Finish Time
41.

............................ is the latest time by which an activity can be finished without delaying the completion of the project.

A. LST
B. LFT
C. EFT
D. EST
Answer» C. EFT
42.

................................is that element of the simplex table which lis both in the key row and key column.

A. Key element
B. Pivot element
C. Both a and b
D. None of these
Answer» D. None of these
43.

An event which represents the beginning of more than one activity is known as ..event.

A. merge
B. net
C. burst
D. none of the above
Answer» D. none of the above
44.

Initial feasible solution to a transportation problem arrived through which of the following method is very near to the optimal solution:

A. NWCM
B. LCM
C. VAM
D. None of these
Answer» D. None of these
45.

a customer s behaviour of leaving the queue when he does not like to wait in the queue due to lack of time or space is called .....................

A. Jockying
B. Reneging
C. Collusion
D. Balking
Answer» E.
46.

A matrix which shows the gains and losses resulting from moves and counter moves is called..................................

A. Cost matrix
B. Pay off matrix
C. Both a and b
D. None of these
Answer» C. Both a and b
47.

Game theory became popular when the book Theory of Games and Economic Behaviour was published in 1944 by ..............................

A. Von Neumann
B. Mc Closky
C. Von-Neumann and Mc Closky
D. Von-neumann and Morgenstern
Answer» E.
48.

In a ........................game the amounts won by all winners together is equal to the sum of the amounts lost by all losers together.

A. Non-zero sum game
B. Zero sum game
C. Rectangular game
D. None of these
Answer» C. Rectangular game
49.

If a simplex table shows the values 2, -3, 0 against , which should be taken as the replacement ratio.

A. 2
B. -3
C. 0
D. None of these ***
Answer» D. None of these ***
50.

When all the players of the game follow their optimal strategies, then the expected pay off of the game is called.......................

A. Gain of the game
B. Loss of the game
C. Value of the game
D. None of these
Answer» D. None of these