MCQOPTIONS
Saved Bookmarks
1. |
..................... is the duration by which an activity can be delayed without delaying the completion of the project. |
A. | Earliest Start Time |
B. | Earliest Finish Time |
C. | Latest Start Time |
D. | Latest Finish Time |
Answer» D. Latest Finish Time | |