

MCQOPTIONS
Saved Bookmarks
1. |
is the time by which the completion of an activity can be delayed beyond its earliest finish time without affecting the earliest start time of a succeeding activity |
A. | slack |
B. | total float |
C. | free float |
D. | independent float |
Answer» D. independent float | |