Explore topic-wise MCQs in Testing Subject.

This section includes 657 Mcqs, each offering curated multiple-choice questions to sharpen your Testing Subject knowledge and support exam preparation. Choose a topic below to get started.

1.

Which model is used to compute the effort required to integrate reusable components or program code that is automatically generated by design or program translation tools?

A. an application-composition model
B. a post-architecture model
C. a reuse model
D. an early design model
Answer» D. an early design model
2.

Which model is used during early stages of the system design after the requirements have been established?

A. an application-composition model
B. a post-architecture model
C. a reuse model
D. an early design model
Answer» E.
3.

Which of the following states that work expands to fill the time available.

A. case tools
B. pricing to win
C. parkinson’s law
D. expert judgement
Answer» D. expert judgement
4.

Which model assumes that systems are created from reusable components, scripting or database programming?

A. an application-composition model
B. a post-architecture model
C. a reuse model
D. an early design model
Answer» B. a post-architecture model
5.

Which technique is applicable when other projects in the same analogy application domain have been completed?

A. algorithmic cost modelling
B. expert judgement
C. estimation by analogy
D. parkinson’s law
Answer» D. parkinson’s law
6.

It is often difficult to estimate size at an early stage in a project when only a specification is available

A. true
B. false
Answer» B. false
7.

A                    is developed using historical cost information that relates some software metric to the project cost.

A. algorithmic cost modelling
B. expert judgement
C. estimation by analogy
D. parkinson’s law
Answer» B. expert judgement
8.

What is related to the overall functionality of the delivered software?

A. function-related metrics
B. product-related metrics
C. size-related metrics
D. none of the mentioned
Answer» B. product-related metrics
9.

Which of the following costs is not part of the total effort cost?

A. costs of networking and communications
B. costs of providing heating and lighting office space
C. costs of lunch time food
D. costs of support staff
Answer» D. costs of support staff
10.

Which of the following are parameters involved in computing the total cost of a software development project?

A. hardware and software costs
B. effort costs
C. travel and training costs
D. all of the mentioned
Answer» E.
11.

The unit of payment of cement concrete in lintels is

A. per sqm
B. per cum
C. quintal
D. kilograms
Answer» C. quintal
12.

The quantity of coarse aggregate required for RCC (1:3:6) for 20 cubic metres of work is

A. 18.24 m3
B. 15.23 m3
C. 24.87 m3
D. 32.45 m3
Answer» B. 15.23 m3
13.

The quantity of sand required for RCC (1:2:4) for 15 cubic metres of work is

A. 4.76 m3
B. 10.32 m3
C. 8.43 m3
D. 6.51 m3
Answer» E.
14.

Which of the following is not a classification of labour?

A. skilled first class
B. skilled second class
C. unskilled
D. unskilled fourth class
Answer» E.
15.

The rates of materials used for government works are approved by

A. executive board
B. sdo
C. elective board
D. board of chief engineers
Answer» E.
16.

Which of the following is the correct order of stages of estimation of concrete roads?

A. earthwork excavations, cement concrete for the base course (1:4:8) and cement concrete for wearing course (1:2:8)
B. earthwork excavations, cement concrete for wearing course (1:4:8) and cement concrete for the base course (1:2:8)
C. earthwork excavations, cement concrete for the base course (1:6:9) and cement concrete for wearing course (1:7:9)
D. cement concrete for the base course (1:2:3), cement concrete for wearing course (2:7:9) and earthwork excavations
Answer» B. earthwork excavations, cement concrete for wearing course (1:4:8) and cement concrete for the base course (1:2:8)
17.

The concrete used for cement concrete roads is of grade

A. m 10
B. m 15
C. m 20
D. m 35
Answer» C. m 20
18.

                                 type of excavator carries the skimmer at its lower end.

A. skimmer
B. dredger
C. escalator
D. elevator
Answer» B. dredger
19.

                                     type of excavator is used for digging at or below the operating level.

A. skimmer
B. dragline
C. power shovel
D. dredger
Answer» C. power shovel
20.

                                 type of excavator carries Shovel at its lower end.

A. power shovel
B. dragline
C. clamshell
D. backactor
Answer» B. dragline
21.

                                   type of excavator is used for digging below, at or above operating level in a vertical range.

A. skimmer
B. dragline
C. clamshell
D. back trench
Answer» D. back trench
22.

                                   type of excavator used for digging the foundation trenches below operating level.

A. clamshell
B. backactor
C. power shovel
D. skimmer
Answer» C. power shovel
23.

An                                is an oldest type of machine which removes earth.

A. escalator
B. excavator
C. elevator
D. bulldozer
Answer» C. elevator
24.

                                 are usually mounted on two or four pneumatic tyred wheels.

A. scraper
B. backactor
C. elevator
D. escalator
Answer» B. backactor
25.

                               consists of a large bucket which is attached to a tractor.

A. bulldozer
B. scraper
C. grader
D. escalator
Answer» C. grader
26.

A Grader which is told by a tractor is known as

A. tractor grader
B. motor grader
C. scraper
D. elevating grader
Answer» E.
27.

                                     type of scraper consists of a four wheeled scrapper bowl towed behind crawler Power unit.

A. three axle
B. two axle
C. crawler drawn
D. four axle
Answer» D. four axle
28.

A                                  can be used on wet ground and in all conditions of weather.

A. grader
B. scraper
C. escalator
D. bulldozer
Answer» E.
29.

A                          is used to level the ground and spreads the loose material.

A. excavator
B. scraper
C. grader
D. tractor
Answer» D. tractor
30.

The size of the bulldozer is indicated by the dimension of its

A. site
B. tyre
C. engine
D. blades
Answer» E.
31.

A                    is very useful equipment and it can be used for construction work like to clear the site of work, to make the land level, etc.

A. scraper
B. grader
C. excavator
D. bulldozer
Answer» E.
32.

                   culverts have a concrete (sometimes other materials can be used too) floor allowing the water to flow smoothly through it.

A. box
B. cylindrical
C. narrow
D. long
Answer» B. cylindrical
33.

Box culverts can be defined as a passage for water over a natural ground having a deck

A. outlighting
B. culverting
C. daylighting
D. inlighting
Answer» D. inlighting
34.

Construction or installation at a culvert site generally results in disturbance of the site soil.

A. true
B. false
Answer» B. false
35.

A culvert can be used to span over a canyon, or depression, or even over a freeway or roadway.

A. true
B. false
Answer» C.
36.

Culverts cannot be constructed of a variety of materials including cast-in-place or precast concrete.

A. true
B. false
Answer» C.
37.

If the span of crossing is greater than 12 feet (3.7 m), the structure is termed as bridge and otherwise is culvert.

A. true
B. false
Answer» B. false
38.

A structure that carries water above land is known as an

A. aqueduct
B. aquedant
C. over surface
D. outland
Answer» B. aquedant
39.

A structure that allows water to flow under a road, railroad, trail, or similar obstruction from one side to the other side is called as

A. drainage
B. bridges
C. tunnel
D. culverts
Answer» E.
40.

What will be the co-efficient of passive earth pressure, at a depth of 8m in cohesion less soil sand with an angle of internal friction of 30° when the water rises to the ground level?

A. 4
B. 5
C. 3
D. 1
Answer» D. 1
41.

The position of the backfill lying above the horizontal plane at the top of wall is called

A. active state
B. plasticity
C. surcharge
D. slip lines
Answer» D. slip lines
42.

The plastic state of stress was proposed by

A. mohr
B. rankine
C. coulomb
D. darcy
Answer» C. coulomb
43.

In active stress, the major principal stress σ1 acting on the wall will be in                       plane.

A. vertical
B. horizontal
C. inclined
D. zero
Answer» C. inclined
44.

The wedge-shaped portion of the backfill tending to move with the wall is called

A. wedge fall
B. active fall
C. failure wedge
D. none of the mentioned
Answer» D. none of the mentioned
45.

The computation of stress in plastic equilibrium is based on

A. theory of plasticity
B. mohr’s theory of rupture
C. rankine’s theory
D. all of the mentioned
Answer» B. mohr’s theory of rupture
46.

The coefficient of earth pressure when the soil is at equilibrium is

A. σv /σh
B. σh /σv
C. σv × σh
D. σ1 / σ3
Answer» C. σv × σh
47.

The material retained or supported by the retaining structure is called

A. surcharge
B. support wall
C. back fill
D. all of the mentioned
Answer» D. all of the mentioned
48.

On designing retaining walls it is necessary to take care of                      exerted by soil mass.

A. erosion
B. lateral pressure
C. surcharge
D. lateral stress
Answer» C. surcharge
49.

A                            houses the squatting pan or toilet seat and provides privacy and protection from the weather for the user.

A. roof
B. terrace
C. shade
D. shelter
Answer» E.
50.

The theory of plasticity pertaining to soils is based on

A. mohr’s theory
B. rankine’s method
C. mohr-coulomb theory
D. none of the mentioned
Answer» B. rankine’s method