Which of the following is the correct order of stages of estimation of concrete roads? |
| A. | earthwork excavations, cement concrete for the base course (1:4:8) and cement concrete for wearing course (1:2:8) |
| B. | earthwork excavations, cement concrete for wearing course (1:4:8) and cement concrete for the base course (1:2:8) |
| C. | earthwork excavations, cement concrete for the base course (1:6:9) and cement concrete for wearing course (1:7:9) |
| D. | cement concrete for the base course (1:2:3), cement concrete for wearing course (2:7:9) and earthwork excavations |
| Answer» B. earthwork excavations, cement concrete for wearing course (1:4:8) and cement concrete for the base course (1:2:8) | |