| 1. |
Latest start of an activity is always |
| A. | greater than or equal to latest event time of preceding node |
| B. | less than or equal to latest event time of preceding node |
| C. | equal to latest event time of preceding node |
| D. | less than latest event time of preceding node |
| Answer» B. less than or equal to latest event time of preceding node | |