In time-cost optimization of a project, crashing is done. |
| A. | On all the activities |
| B. | On all the activities lying on the critical path |
| C. | Only on activities lying on the original critical path and having flatter cost slopes |
| D. | On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope |
| Answer» E. | |