If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is |
| A. | 4 days |
| B. | 6 days |
| C. | 10 days |
| D. | 16 days |
| Answer» E. | |