

MCQOPTIONS
Saved Bookmarks
This section includes 162 Mcqs, each offering curated multiple-choice questions to sharpen your Automobile Engineering knowledge and support exam preparation. Choose a topic below to get started.
1. |
According to Muther, the basic principle of best layout is |
A. | principle of over-all integration |
B. | principle of flow |
C. | principle of flexibility |
D. | all of these |
Answer» E. | |
2. |
In a functional organisation |
A. | quality of work is better |
B. | wastage of material is minimum |
C. | specialised knowledge and guidance to individual worker is provided |
D. | all of the above |
Answer» E. | |
3. |
Which of the following are the principles of material handling? |
A. | keep all the handling to the minimum |
B. | select only efficient handling equipment |
C. | move the heaviest weight to the least distance |
D. | all of the above |
Answer» E. | |
4. |
A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is |
A. | 0.50 |
B. | 0.66 |
C. | 0.84 |
D. | 0.95 |
Answer» D. 0.95 | |
5. |
For material transportation, conveyors are used when the prevailing conditions include |
A. | loads are uniform |
B. | routes do not vary |
C. | materials move relatively continuously |
D. | all of these |
Answer» E. | |
6. |
When slack of an activity is positive |
A. | it represents a situation where extra resources are available and the completion of project is not delayed |
B. | it represents that a programme falls behind schedule and additional resources are required to complete the project in time |
C. | the activity is critical and any delay in its performance will delay the completion of whole project |
D. | any one of the above |
Answer» E. | |
7. |
Break even point is the point where |
A. | fixed and variable cost lines intersect |
B. | fixed and total cost lines intersect |
C. | variable and total cost lines intersect |
D. | sales revenue and total expensive lines intersect |
Answer» E. | |
8. |
The bonus increases in proportion to the increase in efficiency. This statement applies to |
A. | Halsey plan |
B. | Ganttplan |
C. | Emerson's efficiency plan |
D. | Rowan plan |
Answer» D. Rowan plan | |
9. |
M.T.M. is used to |
A. | improve existing methods |
B. | establish time standards |
C. | develop effective methods in advance of the beginning of production |
D. | all of the above |
Answer» E. | |
10. |
F. W. Taylor introduced a system of organisation known as |
A. | line organisation |
B. | functional organisation |
C. | line and staff organisation |
D. | line, staff and functional organisation |
Answer» C. line and staff organisation | |
11. |
The unit cost in case of batch production is __________ as compared to jobbing production. |
A. | same |
B. | low |
C. | high |
D. | None of these |
Answer» C. high | |
12. |
A feasible solution to the linear programming problem should |
A. | satisfy the problem constraints |
B. | optimise the objective function |
C. | satisfy the problem constraints and non-negativity restrictions |
D. | satisfy the non-negativity restrictions |
Answer» D. satisfy the non-negativity restrictions | |
13. |
CPM stands for |
A. | Combined Process Method |
B. | Critical Path Method |
C. | Common Planning Method |
D. | Critical Process Method |
Answer» C. Common Planning Method | |
14. |
Slack may be positive, zero or negative. |
A. | Agree |
B. | Disagree |
C. | Can't say |
D. | None of these |
Answer» B. Disagree | |
15. |
Service time in queuing theory is usually assumed to follow |
A. | normal distribution |
B. | Poissons distribution |
C. | Erlang distribution |
D. | exponential law |
Answer» E. | |
16. |
In a thermal power plant, coal from the coal handling plant is moved to the boiler bunker through a |
A. | belt conveyor |
B. | bucket conveyor |
C. | fork lift truck |
D. | overhead crane |
Answer» B. bucket conveyor | |
17. |
The product layout |
A. | lowers overall manufacturing time |
B. | requires less space for placing machines |
C. | utilises machine and labour better |
D. | all of these |
Answer» E. | |
18. |
Linear programming can be applied successfully to |
A. | chemical industry |
B. | oil industry |
C. | banks |
D. | all of these |
Answer» E. | |
19. |
Process layout is employed |
A. | where low volume of production is required |
B. | where similar jobs are manufactured on similar machines |
C. | where machines are arranged on functional basis |
D. | all of the above |
Answer» E. | |
20. |
The factors which are to be considered while developing a good wage incentive plan will include |
A. | adequate incentive |
B. | ease of administration |
C. | guaranteed basic pay |
D. | all of these |
Answer» E. | |
21. |
Micromotion study is |
A. | analysis of one stage of motion chart |
B. | motion study, when seen on a time chart |
C. | subdivision of an operation into therbligs and their analysis |
D. | enlarged view of motion study |
Answer» D. enlarged view of motion study | |
22. |
PERT is a project planning and control technique. |
A. | Yes |
B. | No |
C. | Can't say |
D. | None of these |
Answer» B. No | |
23. |
In perpetual inventory control, the material is checked as it reaches its |
A. | maximum value |
B. | minimum value |
C. | average value |
D. | any one of these |
Answer» E. | |
24. |
An activity of the project is graphically represented by __________ on the network diagram. |
A. | a circle |
B. | a straight line |
C. | an arrow |
D. | None of these |
Answer» D. None of these | |
25. |
A dummy activity in a net work diagram |
A. | is represented by a dotted line |
B. | is an artificial activity |
C. | does not consume time or resources |
D. | all of these |
Answer» E. | |
26. |
Earliest finish time can be regarded as |
A. | earliest start time + duration of activity |
B. | earliest start time - duration of activity |
C. | latest finish time + duration of activity |
D. | latest finish time - duration of activity |
Answer» B. earliest start time - duration of activity | |
27. |
In inventory control, the economic ordering quantity is obtained by the quantity whose procurement cost is equal to inventory carrying cost. |
A. | True |
B. | False |
C. | Can't say |
D. | None of these |
Answer» B. False | |
28. |
Standard time is equal to |
A. | normal time minus allowances |
B. | normal time plus allowances |
C. | representative time multiplied by rating factor |
D. | normal time taken by an operation |
Answer» C. representative time multiplied by rating factor | |
29. |
CPM requires |
A. | single time estimate |
B. | double time estimate |
C. | triple time estimate |
D. | none of these |
Answer» B. double time estimate | |
30. |
Merit rating is the method of determining the |
A. | relative values of a job |
B. | worker's performance on a job |
C. | worth of a machine |
D. | value of overall production |
Answer» C. worth of a machine | |
31. |
In time study, normal time is more than the standard time. |
A. | Yes |
B. | No |
C. | Can't say |
D. | None of these |
Answer» C. Can't say | |
32. |
Which of the following conditions are necessary for applying linear programming? |
A. | These must be a well defined objective function. |
B. | The decision variables should be interrelated and non-negative. |
C. | The resources must be in limited supply. |
D. | all of the above |
Answer» E. | |
33. |
The type of layout used for manufacturing steam turbines, is |
A. | product layout |
B. | process layout |
C. | fixed position layout |
D. | any one of these |
Answer» D. any one of these | |
34. |
Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is __________ the standard time. |
A. | one-fourth |
B. | one-half |
C. | equal to |
D. | twice |
Answer» C. equal to | |
35. |
If F is the fixed cost, V is the variable cost per unit (or total variable costs) and P is the selling price of each unit (or total sales value), then break even point is equal to |
A. | (F × V)/P |
B. | (F × P)/V |
C. | F/[1 + (V/P)] |
D. | F/[1 - (V/P)] |
Answer» E. | |
36. |
The value engineering technique in which experts of the same rank assemble for product development is called |
A. | Delphi |
B. | brain storming |
C. | morphological analysis |
D. | direct expert comparison |
Answer» C. morphological analysis | |
37. |
A dummy activity becomes a critical activity when its earliest start time (EST) is same as its latest finishing time (LFT). |
A. | Correct |
B. | Incorrect |
C. | Can't say |
D. | None of these |
Answer» B. Incorrect | |
38. |
For handling materials during manufacture of cement, a __________ is widely used. |
A. | belt conveyor |
B. | bucket conveyor |
C. | fork lift truck |
D. | overhead crane |
Answer» C. fork lift truck | |
39. |
P.M.T.S. (Predetermined Motion Time Systems) include |
A. | M.T.M. (Method Time Measurement) |
B. | W.F.S. (Work Factor Systems) |
C. | B.M.T.S. (Basic Motion Time Study) |
D. | all of these |
Answer» E. | |
40. |
Gantt chart gives information about |
A. | scheduling and routing |
B. | sales |
C. | production schedule |
D. | machine utilisation |
Answer» D. machine utilisation | |
41. |
Break even analysis represents the relationship between cost and volume. |
A. | True |
B. | False |
C. | Can't say |
D. | None of these |
Answer» B. False | |
42. |
The start or completion of task is called |
A. | an event |
B. | an activity |
C. | a duration |
D. | none of these |
Answer» B. an activity | |
43. |
The type of organisation preferred for an automobile industry, is |
A. | line organisation |
B. | functional organisation |
C. | line and staff organisation |
D. | line, staff and functional organisation |
Answer» D. line, staff and functional organisation | |
44. |
Actual performance of a task is called |
A. | an event |
B. | an activity |
C. | a duration |
D. | none of these |
Answer» C. a duration | |
45. |
Dummy activities are used to |
A. | determine the critical path |
B. | determine the project completion time |
C. | maintain the required net work |
D. | none of these |
Answer» D. none of these | |
46. |
Halsey plan of wage incentive |
A. | is not applied to all level of workers |
B. | is applied to all level of workers |
C. | does not guarantee minimum wage |
D. | is based upon efficiency of worker |
Answer» C. does not guarantee minimum wage | |
47. |
The production cost per unit can be reduced by |
A. | producing more with increased inputs |
B. | producing more with the same inputs |
C. | eliminating idle time |
D. | minimising resource waste |
Answer» C. eliminating idle time | |
48. |
Break even analysis is a |
A. | short term analysis |
B. | long term analysis |
C. | average of short and long term analysis |
D. | any one of these |
Answer» B. long term analysis | |
49. |
In value engineering, important consideration is given to |
A. | customer satisfaction |
B. | function concept |
C. | profit maximisation |
D. | cost reduction |
Answer» E. | |
50. |
In jobbing production |
A. | highly skilled workers are needed |
B. | unit costs are high |
C. | operations are labour-intensive |
D. | all of these |
Answer» E. | |