A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is |
A. | 0.50 |
B. | 0.66 |
C. | 0.84 |
D. | 0.95 |
Answer» D. 0.95 | |