151. |
Probabilistic time for completion of any activity can be found out from |
A. | optimistic time |
B. | pessimistic time |
C. | most likely time |
D. | all of these |
Answer» E. | |
152. |
Which one of the following chart gives simultaneously information about the progress of work and machine loading? |
A. | Process chart |
B. | Machine load chart |
C. | Man-machine chart |
D. | Gantt chart |
Answer» D. Gantt chart | |
153. |
In a network shown in the below figure, the critical path is along |
A. | 1-2-3-4-8-9 |
B. | 1-2-3-5-6-7-8-9 |
C. | 1-2-3-4-7-8-9 |
D. | 1-2-5-6-7-8-9 |
Answer» C. 1-2-3-4-7-8-9 | |
154. |
When slack of an activity is negative |
A. | it represents a situation where extra resources are available and the completion of project is not delayed |
B. | it represents that a programme falls behind schedule and additional resources are required to complete the project in time |
C. | the activity is critical and any delay in its performance will delay the completion of whole project |
D. | all of the above |
Answer» C. the activity is critical and any delay in its performance will delay the completion of whole project | |
155. |
Work sampling is applied for |
A. | estimation of the percentage utilisation of machine tools |
B. | estimating the percentage of the time consumed by various job activities |
C. | finding out time standards, specially where the job is not repetitive and where time study by stop watch method is not possible |
D. | all of the above |
Answer» E. | |
156. |
A systematic job improvement sequence will consist of |
A. | motion study |
B. | time study |
C. | job enrichment |
D. | all of these |
Answer» E. | |
157. |
In inventory control theory, the economic order quantity is |
A. | average level of inventory |
B. | optimum lot size |
C. | capacity of a warehouse |
D. | lot size corresponding to break-even analysis |
Answer» C. capacity of a warehouse | |
158. |
In value engineering, the term value refers to |
A. | manufacturing cost of the product |
B. | selling price of the product |
C. | total cost of the product |
D. | utility of the product |
Answer» E. | |
159. |
The main object of scientific layout is |
A. | to produce better quality of product |
B. | to utilise maximum floor area |
C. | to minimise production delays |
D. | all of these |
Answer» E. | |
160. |
Gantt chart is used for |
A. | inventory control |
B. | material handling |
C. | production schedule |
D. | machine repair schedules |
Answer» D. machine repair schedules | |
161. |
In time study, the rating factor is applied to determine |
A. | standard time of a job |
B. | merit rating of the worker |
C. | fixation of incentive rate |
D. | normal time of a worker |
Answer» E. | |
162. |
The aim of value engineering is to |
A. | find the depreciation value of a machine |
B. | determine the selling price of a product |
C. | minimise the cost without change in quality of the product |
D. | all of the above |
Answer» D. all of the above | |