Probabilistic time for completion of any activity can be found out from

A. optimistic time
B. pessimistic time
C. most likely time
D. all of these
Answer» E.
152.

Which one of the following chart gives simultaneously information about the progress of work and machine loading?

A. Process chart
B. Machine load chart
C. Man-machine chart
D. Gantt chart
Answer» D. Gantt chart
153.

In a network shown in the below figure, the critical path is along

A. 1-2-3-4-8-9
B. 1-2-3-5-6-7-8-9
C. 1-2-3-4-7-8-9
D. 1-2-5-6-7-8-9
Answer» C. 1-2-3-4-7-8-9
154.

When slack of an activity is negative

A. it represents a situation where extra resources are available and the completion of project is not delayed
B. it represents that a programme falls behind schedule and additional resources are required to complete the project in time
C. the activity is critical and any delay in its performance will delay the completion of whole project
D. all of the above
Answer» C. the activity is critical and any delay in its performance will delay the completion of whole project
155.

Work sampling is applied for

A. estimation of the percentage utilisation of machine tools
B. estimating the percentage of the time consumed by various job activities
C. finding out time standards, specially where the job is not repetitive and where time study by stop watch method is not possible
D. all of the above
Answer» E.
156.

A systematic job improvement sequence will consist of

A. motion study
B. time study
C. job enrichment
D. all of these
Answer» E.
157.

In inventory control theory, the economic order quantity is

A. average level of inventory
B. optimum lot size
C. capacity of a warehouse
D. lot size corresponding to break-even analysis
Answer» C. capacity of a warehouse
158.

In value engineering, the term value refers to

A. manufacturing cost of the product
B. selling price of the product
C. total cost of the product
D. utility of the product
Answer» E.
159.

The main object of scientific layout is

A. to produce better quality of product
B. to utilise maximum floor area
C. to minimise production delays
D. all of these
Answer» E.
160.

Gantt chart is used for

A. inventory control
B. material handling
C. production schedule
D. machine repair schedules
Answer» D. machine repair schedules
161.

In time study, the rating factor is applied to determine

A. standard time of a job
B. merit rating of the worker
C. fixation of incentive rate
D. normal time of a worker
Answer» E.
162.

The aim of value engineering is to

A. find the depreciation value of a machine
B. determine the selling price of a product
C. minimise the cost without change in quality of the product
D. all of the above
Answer» D. all of the above