MCQOPTIONS
Saved Bookmarks
| 1. |
A dummy activity becomes a critical activity when its earliest start time (EST) is same as its latest finishing time (LFT). |
| A. | Correct |
| B. | Incorrect |
| C. | Can't say |
| D. | None of these |
| Answer» B. Incorrect | |