MCQOPTIONS
Saved Bookmarks
This section includes 193 Mcqs, each offering curated multiple-choice questions to sharpen your Civil Engineering knowledge and support exam preparation. Choose a topic below to get started.
| 1. |
Slate |
| A. | Keen's cement. |
| B. | is a metamorphic rock |
| C. | splits into thin sheets along its bedding planes |
| D. | has a smooth surface and contains alumina and silica |
| Answer» B. is a metamorphic rock | |
| 2. |
Pile foundation is generally provided if soil is |
| A. | Mixed bond. |
| B. | compressible |
| C. | water logged |
| D. | made up |
| Answer» E. | |
| 3. |
To obtain good bonding in brick masonry |
| A. | reveals |
| B. | soffits. |
| C. | first class bricks are used |
| D. | vertical joints in alternate courses are kept in plumb line |
| Answer» E. | |
| 4. |
The vertical faces of a door opening which support frame of the door, are |
| A. | Monk bond |
| B. | Rat-trap bond. |
| C. | jambs |
| D. | posts |
| Answer» B. Rat-trap bond. | |
| 5. |
For constructing a terrazo floor. Pick up the incorrect statement from the following : |
| A. | 450 |
| B. | 500 |
| C. | 600 |
| D. | a base course is prepared as in cement concrete flooring |
| Answer» C. 600 | |
| 6. |
Which one of the following rocks is used for monumental buildings : |
| A. | Lime should be slaked before preparing lime mortar |
| B. | High early strength concrete is generally used in cold weather. |
| C. | granite |
| D. | marble |
| Answer» C. granite | |
| 7. |
The process of keeping concrete moist for a certain period after its finishing, is known as |
| A. | jacking |
| B. | piling |
| C. | finishing of concrete |
| D. | curing of concrete |
| Answer» C. finishing of concrete | |
| 8. |
The type of bond in which every course contains both headers and stretchers, is called |
| A. | none of these. |
| B. | English bond |
| C. | Flemish bond |
| D. | Russian band |
| Answer» C. Flemish bond | |
| 9. |
The type of ashlar masonry in which stones are finely chisel dressed and thickness of joints does not exceed 3 mm, is |
| A. | louvered window. |
| B. | chamfered ashlar masonry |
| C. | ashlar facing masonry |
| D. | random coursed ashlar masonry |
| Answer» E. | |
| 10. |
A concrete structure is set on fire and the temperature raises to 1000°C. The strength of concrete as compared to original strength reduces to |
| A. | none of these. |
| B. | 0.1 |
| C. | 0.15 |
| D. | 0.2 |
| Answer» D. 0.2 | |
| 11. |
While designing a stair, the product of rise and going is approximately kept equal to |
| A. | 1/12th of the span |
| B. | 1/15th of the span. |
| C. | 350 |
| D. | 420 |
| Answer» C. 350 | |
| 12. |
While investigating the site, a thick layer of fairly firm clay over a deep layer of soft clay is encountered. In such a situation, the following type of foundation is useful : |
| A. | pile formation |
| B. | raft foundation |
| C. | grillage foundation |
| D. | none of these. |
| Answer» C. grillage foundation | |
| 13. |
If a is the offset of concrete bed in cms, and d is the depth of concrete bed in cms, then |
| A. | none of these. |
| B. | d = 0.445 a |
| C. | 0.557 a |
| D. | d = 0.775 a |
| Answer» D. d = 0.775 a | |
| 14. |
The window which is provided on a sloping roof of a building, is called |
| A. | to increase compaction of the earth retained. |
| B. | lantern window |
| C. | dormer window |
| D. | louvered window |
| Answer» C. dormer window | |
| 15. |
A cut in frame of a door to receive the shutter, is called |
| A. | louver |
| B. | stop |
| C. | horn |
| D. | rebate. |
| Answer» E. | |
| 16. |
In case of multi-storeyed buildings, the forms to be removed first are |
| A. | none of these. |
| B. | sides of beams and girders |
| C. | column forms |
| D. | bottom of beams and girders |
| Answer» B. sides of beams and girders | |
| 17. |
In jack arch floor, the rise is kept |
| A. | all the above. |
| B. | 1/6th of the span |
| C. | 1/8th of the span |
| D. | 1/10th of the span |
| Answer» E. | |
| 18. |
The concrete slump recommended for beams and slabs ; is |
| A. | bat. |
| B. | 25 to 50 mm |
| C. | 25 to 75 mm |
| D. | 30 to 125 mm |
| Answer» D. 30 to 125 mm | |
| 19. |
The wedge shaped bricks forming an arch ring, are called |
| A. | 20 cm |
| B. | 25 cm. |
| C. | Soffits |
| D. | voussoirs |
| Answer» C. Soffits | |
| 20. |
For brick construction, the lime-sand mortar, is |
| A. | 0.042361111111111 |
| B. | 0.043055555555556 |
| C. | 0.04375 |
| D. | 0.044444444444444 |
| Answer» C. 0.04375 | |
| 21. |
The width of the hollow space between two walls of a cavity wall should not exceed |
| A. | b/6. |
| B. | 5 cm |
| C. | 7.5 cm |
| D. | 10 cm |
| Answer» D. 10 cm | |
| 22. |
The highest line of sloping roof, where two oposite slopes meet, is known as |
| A. | all the above. |
| B. | rafter |
| C. | ridge |
| D. | crown |
| Answer» C. ridge | |
| 23. |
The black cotton soil |
| A. | all of these. |
| B. | undergoes volumetric changes |
| C. | swells excessively when wet |
| D. | shrinks excessively when dry |
| Answer» E. | |
| 24. |
Crown is located at |
| A. | highest point on the extrados of the arch |
| B. | highest point on the intrados of the arch |
| C. | skew-back of the arch |
| D. | none of these. |
| Answer» B. highest point on the intrados of the arch | |
| 25. |
The thickness of a reinforced brick partition wall, is generally kept |
| A. | All the above. |
| B. | 5 cm |
| C. | 10 cm |
| D. | 15 cm |
| Answer» C. 10 cm | |
| 26. |
The under surface of an arch, is called |
| A. | soffit |
| B. | intrados |
| C. | haunch |
| D. | back. |
| Answer» B. intrados | |
| 27. |
The process of filling hollow spaces of walls before plastering, is known |
| A. | hacking |
| B. | dubbing out |
| C. | blishering |
| D. | peeling |
| Answer» C. blishering | |
| 28. |
Pick up the correct statement about silt soil from the following : |
| A. | the silt soil has particle size from 0.02 mm to 0.06 mm. |
| B. | in organic fine grained silt soil possesses no plasticity. |
| C. | the least plastic type normally consists of more or less equi-dimensional grains of quartz |
| D. | all the above. |
| Answer» E. | |
| 29. |
Cavity wall is generally provided for |
| A. | heat insulation |
| B. | sound insulation |
| C. | prevention of dampness |
| D. | all the above. |
| Answer» E. | |
| 30. |
The bearing capacity of piles is determined by |
| A. | dynamic formula |
| B. | static formula |
| C. | pile load tests |
| D. | all the above. |
| Answer» E. | |
| 31. |
The brick laid with its length parallel to the face of a wall, is a known as |
| A. | header |
| B. | stretcher |
| C. | closer |
| D. | none of these. |
| Answer» C. closer | |
| 32. |
The nominal thickness of one brick wall in mm, is |
| A. | 90 mm |
| B. | 150 mm |
| C. | 190 mm |
| D. | 200 mm. |
| Answer» E. | |
| 33. |
Brick nogging type of partition wall, is constructed by |
| A. | laying bricks as stretchers in cement mortar |
| B. | laying bricks as headers in cement mortar |
| C. | reinforcing brick wall with iron straps |
| D. | constructing brick work within a wooden framework. |
| Answer» E. | |
| 34. |
Pile foundations are suitable for |
| A. | water logged soils |
| B. | soft rocks |
| C. | compact soils |
| D. | multistoreyed buildings |
| Answer» B. soft rocks | |
| 35. |
The bearing capacity of a water logged soil, may be improved by |
| A. | grouting |
| B. | chemical action |
| C. | drainage |
| D. | compaction. |
| Answer» D. compaction. | |
| 36. |
A floor constructed with the 4 to 6 mm marble chips, is known |
| A. | reinforced marble floor |
| B. | terrazo floor |
| C. | marble floor |
| D. | chip floor |
| Answer» C. marble floor | |
| 37. |
The stone whose crushing strength is maximum, is |
| A. | granite |
| B. | chalk |
| C. | slate |
| D. | sand stone |
| Answer» B. chalk | |
| 38. |
Rotary drilling is the fastest method in case of |
| A. | rocky soils |
| B. | clay soils |
| C. | sandy soil |
| D. | all of these. |
| Answer» E. | |
| 39. |
The bond in which headers and stretchers are laid in alternate courses and every stretcher course is started with a three fourth brick bat, is known as |
| A. | English cross bond |
| B. | Dutch bond |
| C. | Monk bond |
| D. | Rat-trap bond. |
| Answer» C. Monk bond | |
| 40. |
Couple roof is used for spans |
| A. | 3.5 m or less |
| B. | 3.5 m but less than 5 m |
| C. | 5 m but less than 6.5 m |
| D. | 6.5 m but less than 8 m. |
| Answer» B. 3.5 m but less than 5 m | |
| 41. |
The dimensions of a half queen closer, are |
| A. | 9 cm x 9 cm x 9 cm |
| B. | 9 cm x 9 cm x 4.5 cm |
| C. | 9 cm x 4.5 cm x 9 cm |
| D. | 1.8 cm x 4.5 cm x 9 cm. |
| Answer» D. 1.8 cm x 4.5 cm x 9 cm. | |
| 42. |
The service area in a building means the area occupied by |
| A. | stairs |
| B. | toilets |
| C. | light and shafts |
| D. | all the above. |
| Answer» E. | |
| 43. |
Weep holes are provided in retaining and breast walls |
| A. | to drain off the water from the filling |
| B. | to ventilate the stone masonry |
| C. | to add architectural beauty |
| D. | to reduce the weight of the earth retained |
| Answer» B. to ventilate the stone masonry | |
| 44. |
The depth of concrete bed of the foundation depends upon |
| A. | the projection of the concrete block beyond the footing over it |
| B. | the upward soil pressure |
| C. | the mix of the concrete |
| D. | all the above. |
| Answer» E. | |
| 45. |
Pick up the correct statements from the following : |
| A. | cracks appear on the plastered surface in the form of hair cracks |
| B. | in brick work, the efflorescence is removed by applying a solution of zinc sulphate and water |
| C. | excessive thermal variations in the backing or plaster causes the plaster to fall |
| D. | all the above. |
| Answer» E. | |
| 46. |
In ordinary residential and public buildings, the damp proof course is generally provided at |
| A. | ground level |
| B. | plinth level |
| C. | water table level |
| D. | midway ground level and watertable level. |
| Answer» C. water table level | |
| 47. |
For a wall carrying heavy load on low bearing capacity soil, |
| A. | lean concrete bed is provided |
| B. | thick concrete bed is provided |
| C. | reinforced concrete bed is provided |
| D. | (a) and (c) of the above |
| Answer» E. | |
| 48. |
For effective drainage, the finished surface of flat roof should have a minimum slope of |
| A. | 1 in 20 |
| B. | 1 to 50 |
| C. | 1 in 10 |
| D. | 1 in 5. |
| Answer» B. 1 to 50 | |
| 49. |
In case of foundations on sandy soil, maximum permissible differential settlement, is usually limited to |
| A. | 15 mm |
| B. | 25 mm |
| C. | 35 mm |
| D. | 45 mm |
| Answer» C. 35 mm | |
| 50. |
In verandah floors outward slope is |
| A. | 1 in 40 |
| B. | 1 in 50 |
| C. | 1 in 60 |
| D. | 1 in 70 |
| Answer» D. 1 in 70 | |