1. |
The number of blows in Marshalls test specimen is? |
A. | 25 |
B. | 30 |
C. | 55 |
D. | 75 |
Answer» E. | |
2. |
Marshall stability determines __________ |
A. | Ductility |
B. | Flexibility |
C. | Utility |
D. | Grade of bitumen |
Answer» C. Utility | |
3. |
The temperature in Marshall’s method is __________ |
A. | 25 |
B. | 30 |
C. | 35 |
D. | 60 |
Answer» E. | |
4. |
The specified method for bitumen mix in India is? |
A. | Hveem |
B. | Marshalls method |
C. | Hubbard method |
D. | Super paver mix method |
Answer» C. Hubbard method | |
5. |
Volume of mineral aggregate is? |
A. | VV+VB |
B. | Vv-Vb |
C. | VV*Vb |
D. | VV/VB |
Answer» B. Vv-Vb | |
6. |
The specific gravity of bitumen lies between __________ |
A. | 0.8 & 0.9 |
B. | 0.95 & 0.97 |
C. | 0.97 & 1.02 |
D. | 1.02 & 1.05 |
Answer» D. 1.02 & 1.05 | |
7. |
Maximum size of aggregate in surface course is? |
A. | 18.5mm |
B. | 19.5mm |
C. | 20.5mm |
D. | 21.5mm |
Answer» B. 19.5mm | |
8. |
Maximum size of aggregate in base course is? |
A. | 25 mm |
B. | 50 mm |
C. | 40 mm |
D. | 30 mm |
Answer» C. 40 mm | |
9. |
Bleeding may be avoided by __________ |
A. | Water voids |
B. | Air voids |
C. | Porosity |
D. | Water content |
Answer» C. Porosity | |
10. |
Rutting may be avoided by __________ |
A. | Good compaction |
B. | Good aggregate |
C. | Good filler |
D. | Good workmanship |
Answer» C. Good filler | |
11. |
The filler material should pass from __________ |
A. | 0.075mm |
B. | 0.75mm |
C. | 7.5mm |
D. | 75mm |
Answer» B. 0.75mm | |
12. |
The DBM is used in __________ |
A. | Local streets |
B. | Rural roads |
C. | Highway |
D. | Concrete bridges |
Answer» D. Concrete bridges | |
13. |
The surface of bitumen should be __________ |
A. | Smooth |
B. | Rough |
C. | Sufficient enough to resist friction |
D. | Very smooth |
Answer» D. Very smooth | |
14. |
MAXIMUM_SIZE_OF_AGGREGATE_IN_SURFACE_COURSE_IS?$ |
A. | 18.5mm |
B. | 19.5mm |
C. | 20.5mm |
D. | 21.5mm |
Answer» B. 19.5mm | |
15. |
Volume of mineral aggregate is$ |
A. | VV+VB |
B. | Vv-Vb |
C. | VV*Vb |
D. | VV/VB |
Answer» B. Vv-Vb | |
16. |
The_specific_gravity_of_bitumen_lies_between$ |
A. | 0.8& 0.9 |
B. | 0.95& 0.97 |
C. | 0.97&1.02 |
D. | 1.02&1.05 |
Answer» D. 1.02&1.05 | |
17. |
The number of blows in Marshalls test specimen is |
A. | 25 |
B. | 30 |
C. | 55 |
D. | 75 |
Answer» E. | |
18. |
Marshall stability determines |
A. | Ductility |
B. | Flexibility |
C. | Utility |
D. | Grade of bitumen |
Answer» C. Utility | |
19. |
The temperature in Marshall’s method is$ |
A. | 25 |
B. | 30 |
C. | 35 |
D. | 60 |
Answer» E. | |
20. |
The_specified_method_for_bitumen_mix_in_India_is |
A. | Hveem |
B. | Marshalls method |
C. | Hubbard method |
D. | Super paver mix method |
Answer» C. Hubbard method | |
21. |
Maximum size of aggregate in base course i? |
A. | 25 mm |
B. | 50 mm |
C. | 40 mm |
D. | 30 mm |
Answer» C. 40 mm | |
22. |
Which aggregate produce higher stability of mix? |
A. | Gravel |
B. | Sharp sand |
C. | Rounded sand |
D. | Fly ash |
Answer» C. Rounded sand | |
23. |
Bleeding may be avoided by |
A. | Water voids |
B. | Air voids |
C. | Porosity |
D. | Water content |
Answer» C. Porosity | |
24. |
Rutting may be avoided by |
A. | Good compaction |
B. | Good aggregate |
C. | Good filler |
D. | Good workmanship |
Answer» C. Good filler | |
25. |
The filler material should pass from |
A. | 0.075mm |
B. | 0.75mm |
C. | 7.5mm |
D. | 75mm |
Answer» B. 0.75mm | |
26. |
The DBM is used in |
A. | Local streets |
B. | Rural roads |
C. | Highway |
D. | Concrete bridges |
Answer» D. Concrete bridges | |
27. |
The surface of bitumen should be |
A. | Smooth |
B. | Rough |
C. | Sufficient enough to resist friction |
D. | Very smooth |
Answer» D. Very smooth | |
28. |
Which layer of pavement should withstand stress? |
A. | Surface |
B. | Sub grade |
C. | Sub base |
D. | Base |
Answer» B. Sub grade | |