1. |
The site amenities are covered under which of the items of DPR? |
A. | Background |
B. | Abstract |
C. | Miscellaneous |
D. | Estimate |
Answer» D. Estimate | |
2. |
For small projects which type of method is used for the calculation of project time? |
A. | Milestone chart |
B. | Bar chart |
C. | PERT |
D. | CPM |
Answer» C. PERT | |
3. |
The strength of the materials can be checked by ___________ |
A. | Visual inspection |
B. | Quality control |
C. | By asking the manufacturer |
D. | By referring to various codes |
Answer» C. By asking the manufacturer | |
4. |
The final step in the specifications and design of roadway elements is ___________ |
A. | Specifications |
B. | Design elements |
C. | Geometric design |
D. | Safety and audit of the design elements |
Answer» E. | |
5. |
The roadway features include the study of ___________ |
A. | Accidental analysis |
B. | Geometric design |
C. | Route alignment |
D. | Safety |
Answer» D. Safety | |
6. |
The first step in the detail checklist of DPR is ___________ |
A. | Executive summary |
B. | Background |
C. | Roadway features |
D. | General details of the project |
Answer» B. Background | |
7. |
THE_SITE_AMENITIES_ARE_COVERED_UNDER_WHICH_OF_THE_ITEMS_OF_DPR??$ |
A. | Background |
B. | Abstract |
C. | Miscellaneous |
D. | Estimate |
Answer» D. Estimate | |
8. |
Which of the following is prepared first during estimate? |
A. | Schedule of rates |
B. | Rate analysis |
C. | Detailed cost estimate |
D. | Detailed project |
Answer» B. Rate analysis | |
9. |
For small projects which type of method is used for calculation of project time? |
A. | Milestone chart |
B. | Bar chart |
C. | PERT |
D. | CPM |
Answer» C. PERT | |
10. |
The strength of the materials can be checked by |
A. | Visual inspection |
B. | Quality control |
C. | By asking the manufacturer |
D. | By referring to various codes |
Answer» C. By asking the manufacturer | |
11. |
Which of the following is not a structure constructed for drainage purposes? |
A. | Aqueduct |
B. | Syphon aqueduct |
C. | Level crossing |
D. | Pitot tube |
Answer» E. | |
12. |
The final step in the specifications and design of roadway elements is |
A. | Specifications |
B. | Design elements |
C. | Geometric design |
D. | Safety and audit of the design elements |
Answer» E. | |
13. |
The roadway features include the study of |
A. | Accidental analysis |
B. | Geometric design |
C. | Route alignment |
D. | Safety |
Answer» D. Safety | |
14. |
The name of the work and project details is managed under which category of DPR? |
A. | Executive summary |
B. | Background |
C. | Roadway details |
D. | General details |
Answer» C. Roadway details | |
15. |
The first step in the detail checklist of DPR is |
A. | Executive summary |
B. | Background |
C. | Roadway features |
D. | General details of the project |
Answer» B. Background | |
16. |
The DPR consists of how many components? |
A. | One |
B. | Two |
C. | Three |
D. | Four |
Answer» D. Four | |