				| 1. | 
                                    Which of the following is not a part of holding TPM kick-off? | 
                            
| A. | Announcing to top management about the decision to introduce TPM | 
| B. | Invite client companies | 
| C. | Invite affiliated companies | 
| D. | Invite subcontracting companies | 
| Answer» B. Invite client companies | |