

MCQOPTIONS
Saved Bookmarks
1. |
Match the columns(i) Activity Ratio -------------------- i) (Actual hours worked / Budgeted hours) * 100(ii) Capacity Ratio ------------------ ii) (Standard hours of actual production / Actual hours worked) * 100(iii) Efficiency Ratio ----------------- iii) (Standard hours for actual output / Budgeted hours) * 100 |
A. | A-ii, B-iii, C-i |
B. | A-i, B-ii, C-iii |
C. | A-iii, B-i, C-ii |
D. | None of the above |
Answer» D. None of the above | |