| 1. |
Calculate Takt Time when there are 500 minutes in work day and the customer demand is 500 units a day. |
| A. | 1 minute |
| B. | 2 minutes |
| C. | 3 minutes |
| D. | 4 minutes |
| Answer» B. 2 minutes | |