Calculate number of Kanbans if the hourly demand is 200 units, lead time is 12 hours, container capacity is 144 units, and variation in lead time is 15%. |
| A. | 23 |
| B. | 22 |
| C. | 21 |
| D. | 20 |
| Answer» E. | |