1. |
The site amenities are covered under which of the items of DPR? |
A. | Background |
B. | Abstract |
C. | Miscellaneous |
D. | Estimate |
Answer» D. Estimate | |
2. |
For small projects which type of method is used for the calculation of project time? |
A. | Milestone chart |
B. | Bar chart |
C. | PERT |
D. | CPM |
Answer» C. PERT | |
3. |
The strength of the materials can be checked by ___________ |
A. | Visual inspection |
B. | Quality control |
C. | By asking the manufacturer |
D. | By referring to various codes |
Answer» C. By asking the manufacturer | |
4. |
The final step in the specifications and design of roadway elements is ___________ |
A. | Specifications |
B. | Design elements |
C. | Geometric design |
D. | Safety and audit of the design elements |
Answer» E. | |
5. |
The roadway features include the study of ___________ |
A. | Accidental analysis |
B. | Geometric design |
C. | Route alignment |
D. | Safety |
Answer» D. Safety | |
6. |
The first step in the detail checklist of DPR is ___________ |
A. | Executive summary |
B. | Background |
C. | Roadway features |
D. | General details of the project |
Answer» B. Background | |