			MCQOPTIONS
 Saved Bookmarks
				This section includes 3 Mcqs, each offering curated multiple-choice questions to sharpen your Waste Water Engineering knowledge and support exam preparation. Choose a topic below to get started.
| 1. | Which of the following is considered if sewers are placed on the softer grounds? | 
| A. | tThe trench is excavated to confirm the shape of the pipe | 
| B. | tSewers are laid embedded in the concrete | 
| C. | tThe width of the trench is kept to 15 cm | 
| D. | tThe desired slope is considered | 
| Answer» C. tThe width of the trench is kept to 15 cm | |
| 2. | The depth in open drain should preferably be kept _______ the man height. | 
| A. | tLess than | 
| B. | tGreater than | 
| C. | tEqual to | 
| D. | tSufficient to | 
| Answer» B. tGreater than | |
| 3. | Storm water is collected from streets into the __________ which in turn discharged into main drains of open type. | 
| A. | tLink drains | 
| B. | tLateral drains | 
| C. | tSub mains | 
| D. | tInterseptal mains | 
| Answer» B. tLateral drains | |