101. |
An optimum project schedule implies |
A. | Optimum utilization of men, machines and materials |
B. | Lowest possible cost and shortest possible time for project |
C. | Timely execution of project |
D. | To produce best results under given constraints |
Answer» C. Timely execution of project | |
102. |
Pick up the incorrect statement from the following. A critical ratio scheduling |
A. | Establishes the relative priorities among various activities on a common basis |
B. | Determines the status of each activity |
C. | Adjusts automatically changes in activity progress |
D. | None of the above |
Answer» E. | |
103. |
Monte Carlo solutions in queuing theory are extremely useful in queuing problems |
A. | That can't be analysed mathematically |
B. | Involving multistage queuing |
C. | To verify mathematical results |
D. | All of the above |
Answer» B. Involving multistage queuing | |
104. |
The break-even point represents |
A. | The most economical level of operation of any industry |
B. | The time when unit can run without any loss and profit |
C. | Time when industry will undergo loss |
D. | The time when company can make maximum profits |
Answer» C. Time when industry will undergo loss | |
105. |
In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker |
A. | Whose output exceeds 67% efficiency |
B. | On the percentage of time saved |
C. | On the percentage of time worked |
D. | On the percentage of standard time |
Answer» B. On the percentage of time saved | |
106. |
According to Rowan plan of wage incentive system, bonus is paid to a worker |
A. | Whose output exceeds 67% efficiency |
B. | On the percentage of time saved |
C. | On the percentage of time worked |
D. | On the percentage of standard time |
Answer» D. On the percentage of standard time | |
107. |
In order to avoid excessive multiplication of facilities, the layout preferred is |
A. | Product layout |
B. | Process layout |
C. | Group layout |
D. | Static layout |
Answer» C. Group layout | |
108. |
If a worker gets a daily wage of Rs HA, then according to Rowan plan, his maximum daily earnings can be |
A. | 2 HA |
B. | 1.33 HA |
C. | 1.5 HA |
D. | 1.15 HA |
Answer» B. 1.33 HA | |
109. |
The probability distribution of project completion in PERT follows following distribution |
A. | Normal |
B. | Binomial |
C. | Exponential |
D. | Gaussian |
Answer» E. | |
110. |
The probability distribution of activity times in PERT follows following distribution |
A. | Normal |
B. | Binomial |
C. | Beta |
D. | Exponential |
Answer» D. Exponential | |
111. |
PERT/CPM, techniques can be used for following applications |
A. | Once through project |
B. | Maintenance jobs |
C. | Research and development |
D. | All of the above |
Answer» E. | |
112. |
The deductions for, employees provident fund start |
A. | Immediately on joining the service |
B. | After 60 days of joining the service |
C. | After 100 days of joining the service |
D. | After 240 days of joining the service |
Answer» E. | |
113. |
Breakeven analysis is a |
A. | Short term analysis |
B. | Long term analysis |
C. | Average of short and long term analysis |
D. | Any one of these |
Answer» B. Long term analysis | |
114. |
The correct sequence of phases in value engineering is |
A. | Creative phase, information phase, investigation phase, evaluation phase |
B. | Information phase, creative phase, investigation phase, evaluation phase |
C. | Investigation phase, information phase, creative phase, evaluation phase |
D. | Creative phase, investigation phase, evaluation phase, information phase |
Answer» B. Information phase, creative phase, investigation phase, evaluation phase | |
115. |
Standard time as compared to normal time is |
A. | Greater |
B. | Smaller |
C. | Equal |
D. | There is no such correlation |
Answer» B. Smaller | |
116. |
One of the basic essentials of an incentive plan is that |
A. | A differential piece rate system should exist |
B. | Minimum wages should be guaranteed |
C. | Provide incentive to group efficiency performance |
D. | All standards should be based on time studies |
Answer» E. | |
117. |
Time study is |
A. | The appraisal, in terms of time, of the value of work involving human effort |
B. | Machine setting time |
C. | Time taken by workers to do a job |
D. | Method of fixing time for workers |
Answer» B. Machine setting time | |
118. |
The standard time for a job is |
A. | Total work content |
B. | Base time + relaxation time |
C. | Total work content + basic time |
D. | Total work content + delay contingency allowance |
Answer» E. | |
119. |
The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as |
A. | Duration |
B. | Total float |
C. | Free float |
D. | Interfering float |
Answer» D. Interfering float | |
120. |
Valve analysis is particularly of interest when |
A. | Jobbing work economics are involved |
B. | Production is on large scale |
C. | Only few components are involved |
D. | Costly equipment is used |
Answer» C. Only few components are involved | |
121. |
Which of the following statement is correct about the network diagram? |
A. | The events are represented graphically by circles or nodes at the beginning and the end of activity by arrows. |
B. | The tail end of the arrow represents the start of an activity. |
C. | The head of the arrow represents the end of an activity. |
D. | All of the above |
Answer» E. | |
122. |
Which of the following are the guidelines for the construction of a network diagram? |
A. | Each activity is represented by one and only one arrow in the network |
B. | Dangling must be avoided in a network diagram |
C. | Dummy activity consumes no time or resource |
D. | All of the above |
Answer» E. | |
123. |
The type of organisation preferred for a steel industry, is |
A. | Line organisation |
B. | Functional organisation |
C. | Line and staff organisation |
D. | Line, staff and functional organisation |
Answer» E. | |
124. |
A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is |
A. | 0.50 |
B. | 0.66 |
C. | 0.84 |
D. | 0.95 |
Answer» D. 0.95 | |
125. |
The type of layout used for manufacturing steam turbines, is |
A. | Product layout |
B. | Process layout |
C. | Fixed position layout |
D. | Any one of these |
Answer» D. Any one of these | |
126. |
Bar chart is suitable for |
A. | Large project |
B. | Major work |
C. | Minor work |
D. | All of these |
Answer» D. All of these | |
127. |
Product layout is employed for |
A. | Batch production |
B. | Continuous production |
C. | Effective utilization of machine |
D. | All of the above |
Answer» C. Effective utilization of machine | |
128. |
Process layout is employed for |
A. | Batch production |
B. | Continuous type of product |
C. | Effective utilization of machines |
D. | All of the above |
Answer» B. Continuous type of product | |
129. |
The basic difference between PERT and CPM is that |
A. | PERT deals with events and CPM with activities |
B. | Critical path is determined in PERT only |
C. | Costs are considered on CPM only and not in PERT |
D. | Guessed times are used in PERT and evaluated times in CPM |
Answer» E. | |
130. |
Choose the wrong statement. Motion study is used for |
A. | Improving a work method |
B. | Improvising a work method |
C. | Designing a work method |
D. | Reducing inventory costs |
Answer» E. | |
131. |
The appellate authority for an industrial dispute is |
A. | Management |
B. | Labour court |
C. | High court/supreme court |
D. | Board of directors |
Answer» D. Board of directors | |
132. |
Pessimistic time is |
A. | The maximum time which an activity might require |
B. | The average time required for a job |
C. | The most probable time considering all conditions |
D. | The minimum time in which an activity can possibly be accomplished |
Answer» B. The average time required for a job | |
133. |
'Value' for value engineering and analysis purposes is defined as |
A. | Purchase value |
B. | Saleable value |
C. | Depreciated value |
D. | Function/cost |
Answer» E. | |
134. |
Scheduling |
A. | Prescribes the sequence of operations to be followed |
B. | Determines the programme for the operations |
C. | Is concerned with starting of processes |
D. | Regulates the progress of job through various processes |
Answer» C. Is concerned with starting of processes | |
135. |
Which of the following plans motivates supervisors by paying a premium on time saved by workers? |
A. | Halsey plan |
B. | Rowan plan |
C. | Haynes plan |
D. | Emerson's plan |
Answer» D. Emerson's plan | |
136. |
Break-even point is the point where |
A. | Fixed and variable cost lines intersect |
B. | Fixed and total cost lines intersect |
C. | Variable and total cost lines intersect |
D. | Sales revenue and total expensive lines intersect |
Answer» E. | |
137. |
A company spends considerable amount on publicity to promote sales. This expenditure in break even chart is shown below the |
A. | Fixed cost line |
B. | Variable cost line |
C. | Total cost line |
D. | Sales revenue line |
Answer» C. Total cost line | |
138. |
Work study is mainly aimed at |
A. | Determining the most efficient method of performing a job |
B. | Establishing the minimum time of completion of a job |
C. | Developing the standard method and standard time of a job |
D. | Economizing the motions involved on the part of the worker while performing a job |
Answer» B. Establishing the minimum time of completion of a job | |
139. |
Break-even analysis can be used for |
A. | Short run analysis |
B. | Long run analysis |
C. | Average of above two run analysis |
D. | There is no such criterion |
Answer» B. Long run analysis | |
140. |
Queuing theory is associated with |
A. | Sales |
B. | Inspection time |
C. | Waiting time |
D. | Production time |
Answer» D. Production time | |
141. |
Discrepancies of bar chart techniques are |
A. | Consequential effects of lack in one activity on the finish date |
B. | Free time available for an activity can't be predicted |
C. | Effective monitoring/controlling can't be done |
D. | All of the above |
Answer» E. | |
142. |
PERT is applied for |
A. | Marketing programmes and advertising programmes |
B. | Installation of machinery |
C. | Research and development of products |
D. | All of these |
Answer» E. | |
143. |
Routing |
A. | Prescribes the sequence of operations to be followed |
B. | Determines the programme for the operations |
C. | Is concerned with starting of processes |
D. | Regulates the progress of job through various processes |
Answer» B. Determines the programme for the operations | |
144. |
Pick up the incorrect statement from the following |
A. | An activity of the project is denoted by an arrow on the net work |
B. | The tail of the arrow indicates the start of the activity |
C. | The head of the arrow indicates the end of the activity |
D. | The arrows are drawn (to scale from) left to right |
Answer» E. | |
145. |
Gantt chart provides information about the |
A. | Material handling |
B. | Proper utilization of manpower |
C. | Production schedule |
D. | Efficient working of machine |
Answer» D. Efficient working of machine | |
146. |
Work study involves |
A. | Only method study |
B. | Only work measurement |
C. | Method study and work measurement |
D. | Only motion study |
Answer» D. Only motion study | |
147. |
Slack represents the difference between the |
A. | Latest allowable time and the normal expected time |
B. | Latest allowable time and the earliest expected time |
C. | Proposed allowable time and the earliest expected time |
D. | Normal allowable time and the latest expected time |
Answer» C. Proposed allowable time and the earliest expected time | |
148. |
TMU in method time measurement stands for |
A. | Time motion unit |
B. | Time measurement unit |
C. | Time movement unit |
D. | Technique measurement unit |
Answer» C. Time movement unit | |
149. |
Emergency rush order can be pushed more effectively in |
A. | Job production |
B. | Automatic production |
C. | Continuous production |
D. | Intermittent production |
Answer» E. | |
150. |
Graphical method, simplex method, and transportation method are concerned with |
A. | Break-even analysis |
B. | Value analysis |
C. | Linear programming |
D. | Queueing theory |
Answer» D. Queueing theory | |