51.

Pick up the correct statement from the following i.

A. Higher workability indicates unexpected increase in the moisture content
B. Higher workability indicates deficiency of sand
C. If the concrete mix is dry, the slump is zero
D. Concrete mix having zero slump, is unsuitable for high strength.
Answer» E.
52.

Batching error means inaccuracy in the quantity of

A. aggregates
B. cement
C. water
D. all the above.
Answer» E.
53.

The shuttering of a hall measuring 4 m x 5 m, can be removed after

A. 5 days
B. 7 days
C. 10 days
D. 14 days
Answer» C. 10 days
54.

For concreting tunnel linings, tran-portation of concrete is done by

A. pans
B. wheel borrows
C. containers
D. pumps
Answer» E.
55.

If the effective plan area of a warehouse is 54 sq. m, and maximum height of piles permitted is 270 cm, the number of cement bags to be stored, is

A. 2000 bags
B. 2200 bags
C. 2400 bags
D. 2700 bags
Answer» E.
56.

1.S.I. has specified the full strength of concrete after

A. 7 days
B. 14 days
C. 21 days
D. 28 days
Answer» E.
57.

Gypsum is added for

A. colour
B. strength
C. controlling setting time
D. none of these.
Answer» D. none of these.
58.

The strength and quality of concrete, depend upon:

A. grading of aggregates
B. surface area of aggregates
C. shape of aggregates
D. surface texture of aggregates
Answer» E.
59.

C.R.R.I. charts are used to obtain a relatioship between strength of concrete and

A. water cement ratio
B. workability
C. grading of aggregate
D. fineness modulus
Answer» B. workability
60.

The surface where two successive placements of concrete meet, is known as

A. Contraction joint
B. Expansion joint
C. Construction joint
D. both (a) and (b)
Answer» D. both (a) and (b)
61.

The maximum percentage of chemical ingredient of cement is that of

A. magnesium oxide
B. iron oxide
C. aluminium
D. lime
Answer» E.
62.

An aggregate is known as cyclopean aggregate if its size is more than

A. 4.75 mm
B. 30 mm
C. 60 mm
D. 75 mm
Answer» E.
63.

Expansion joints are provided if the length of concrete structures exceeds

A. 10 m
B. 15 m
C. 15 m
D. 35 m
Answer» E.
64.

Curing of pavements, floors, roofs and slabs, is done by

A. membrane method
B. ponding method
C. covering surface with bags
D. sprinkling water method
Answer» C. covering surface with bags
65.

For the construction of cement con-certe dams, the maximum permissible size of the aggregates, is

A. 40 mm
B. 50 mm
C. 60 mm
D. 70 mm
Answer» B. 50 mm
66.

In slump test, each layer of concrete is compacted by a steel rod 60 cm long and of 16 mm diameter for

A. 20 times
B. 25 times
C. 30 times
D. 40 times
Answer» C. 30 times
67.

While designing an air entrained concrete

A. water cement ratio is reduced
B. proportion of aggregates is reduced
C. an allowance for the entrained air is made
D. strength of the concrete, is reduced
Answer» E.
68.

An aggregate which passes through 25 mm I.S. sieve and is retained on 20 mm sieve, is said to be flaky if its least dimension is less than

A. 22.5 mm
B. 18.5 mm
C. 16.5 mm
D. 15.5 mm
Answer» E.
69.

Higher workability of concrete is required if the structure is

A. made with cement concrete
B. thick and reinfored
C. thin and heavily reinforced
D. thick and heavily reinfored.
Answer» E.
70.

The operation of removing humps and hollows of uniform concrete surface, is known as

A. floating
B. screeding
C. trowelling
D. finishing
Answer» C. trowelling
71.

The condition not applicable to water cement ratio law, is

A. internal moisture conditions on hydration continue till complete strength is gained
B. concrete specimens may be tested at any temperature
C. concrete specimens need be of same age
D. concrete specimens need be of same size
Answer» C. concrete specimens need be of same age
72.

The process of mixing, transporting, placing and compacting concrete using Ordinary Port land Cement should not take more than

A. 30 minutes
B. 40 minutes
C. 60 minutes
D. 75 minutes
Answer» B. 40 minutes
73.

The grade of concrete not recommended by I.S. : 456, is

A. M 100
B. M 200
C. M 300
D. M 400
Answer» E.
74.

The cement whose strength is a little lower than the ordinary cement during the first three months but attains afterwards the same strength, is known as

A. low-heat Portland cement
B. rapid hardening Portland cement
C. Portland blast slag cement
D. Portland pozzolana cement
Answer» B. rapid hardening Portland cement
75.

To prevent segregation, the maximum height for placing concrete, is

A. 100 cm
B. 125 cm
C. 150 cm
D. 200 cm
Answer» B. 125 cm
76.

Particles of 0.002 mm size are that of

A. clay
B. sand
C. gravel
D. none of these.
Answer» B. sand
77.

Workability of concrete for a given water content is good if the aggregates, are

A. rounded aggregate
B. irregular aggregate
C. angular aggregate
D. flaky aggregates.
Answer» B. irregular aggregate
78.

Water cement ratio is generally expressed in volume of water required per

A. 10 kg
B. 20 kg
C. 30 kg
D. 40 kg
Answer» E.
79.

The type of aggregates of same nominal size, which contain less voids when compacted, are

A. rounded spherical
B. irregular
C. flaky
D. none of these.
Answer» B. irregular
80.

Workability improved by adding

A. fly ash
B. hydrated lime
C. calcium chloride
D. bentonite
Answer» E.
81.

A concrete having a slump of 6.5 cm, is said to be

A. dry
B. earth moist
C. semi-plastic
D. plastic
Answer» E.
82.

Too wet concrete may cause

A. weakness of concrete
B. excessive laitance
C. segregation
D. lower density
Answer» E.
83.

If 50 kg of fine aggregates and 100 kg of coarse agregates are mixed in a concrete whose water cement ratio is 0.6, the weight of water required for harsh mix, is

A. 8 kg
B. 10 kg
C. 12 kg
D. 14 kg
Answer» D. 14 kg
84.

Sand requiring a high water cement ratio, belongs to

A. Zone I
B. Zone II
C. Zone III
D. Zone IV.
Answer» B. Zone II
85.

Workability of concrete mix with low water cement ratio is determined by

A. tensile strength test
B. slump test
C. compaction factor test
D. flexural strength test
Answer» D. flexural strength test
86.

If the depth of moist sand in a cylinder is 15 cm and the depth of the sand when fully inundated with water is 12 cm, the bulking of the moist sand, is

A. 0.1
B. 0.12
C. 0.15
D. 0.2
Answer» E.
87.

The specifications of a cement bag for storage, are

A. weight 50 kg
B. height 18 cm
C. plan area 3000 sq. cm
D. volume 35 litres
Answer» E.
88.

Strength of concrete with passage of time

A. increases
B. decreases
C. fluctuates
D. remains constant.
Answer» B. decreases
89.

Addition of pozzolana to cement

A. decreases workability
B. increases strength
C. increases heat of hydration
D. decreases curing time
Answer» E.
90.

If the effective working time is 7 hours and per batch time of concrete is 3 minutes, the output of a concrete mixer of 150 litre capacity, is

A. 15, 900 litres
B. 16, 900 litres
C. 17, 900 litres
D. 18, 900 litres
Answer» E.
91.

An ordinary Portland cement when tested for its fineness, should not leave any residue on I.S. seive No. 9, more than

A. 0.05
B. 0.1
C. 0.15
D. 0.2
Answer» C. 0.15
92.

The top diameter, bottom diameter and the height of a slump mould are :

A. 10 cm, 20 cm, 30 cm
B. 10 cm, 30 cm, 20 cm
C. 20 cm, 10 cm, 30 cm
D. 20 cm, 30 cm, 10 cm
Answer» B. 10 cm, 30 cm, 20 cm
93.

Placing of concrete should preferably be done at a temperature of

A. 0°C
B. 10°C
C. 20°C
D. 23°C
Answer» E.
94.

Bulking of sand is

A. mixing of different sizes of sand particles
B. mixing of lime with sand
C. maximum water with sand
D. swelling of sand when wetted.
Answer» E.
95.

The void ratio of

A. single size coarse aggregate is roughly 0.45.
B. graded coarse aggregate is roughly 0.040
C. fine aggregate is roughly 0.45
D. all the above.
Answer» E.
96.

You are asked to construct a massive dam, the type of cement you will use, is

A. ordinary Portland cement
B. rapid hardening cement
C. low heat cement
D. blast furnace slag cement
Answer» D. blast furnace slag cement
97.

Horizontal construction joints in concrete walls are generally provided at

A. soffit level
B. window sill level
C. floor level
D. all the above.
Answer» E.
98.

The main object of compaction of concrete, is:

A. to eliminate air holes
B. to achieve maximum density
C. to provide initimate contact between the concrete and embedded materials
D. all the above.
Answer» E.
99.

If the average compressive strength is 4000 kg/cm2 and standard deviation is 500, the co-efficient of variation is

A. 0.1
B. 0.125
C. 0.15
D. 0.185
Answer» C. 0.15
100.

The percentage of the aggregate of F.M. 2.6 to be combined with coarse aggregate of F.M. 6.8 for obtaining the aggregates of F.M. 5.4, is

A. 0.3
B. 0.4
C. 0.5
D. 60%.
Answer» D. 60%.