1. |
The absolute minimum radius of the curve in snow bound area is __________ |
A. | 60 m |
B. | 70 m |
C. | 80 m |
D. | 90 m |
Answer» B. 70 m | |
2. |
The minimum sufficient straight distance between the transitional ends for reverse curves is __________ |
A. | 3.0 m |
B. | 5.0 m |
C. | 9.0 m |
D. | 12.0 m |
Answer» D. 12.0 m | |
3. |
What is the maximum super elevation on snow bound area? |
A. | 3.0% |
B. | 5.0% |
C. | 7.0% |
D. | 10.0% |
Answer» D. 10.0% | |
4. |
What is the intermediate sight distance for a speed limit of 50 Kmph? |
A. | 120 m |
B. | 60 m |
C. | 40 m |
D. | 30 m |
Answer» B. 60 m | |
5. |
What is the stopping sight distance for a speed limit of 50 Kmph? |
A. | 30 m |
B. | 40 m |
C. | 60 m |
D. | 120 m |
Answer» D. 120 m | |
6. |
The camber for the earth roads should be never less than __________ |
A. | 4% |
B. | 3.75% |
C. | 3.5% |
D. | 3.0% |
Answer» E. | |
7. |
The flatter camber may be provided if the road has a longitudinal gradient greater than __________ |
A. | 1 in 40 |
B. | 1 in 35 |
C. | 1 in 30 |
D. | 1 in 20 |
Answer» E. | |
8. |
The pavement width for a single lane road on a hill is __________ |
A. | 3.5 m |
B. | 3.75 m |
C. | 7.0 m |
D. | 7.5 m |
Answer» E. | |
9. |
What is the minimum right of way distance in exceptional cases? |
A. | 7 m |
B. | 5 m |
C. | 3 m |
D. | 4 m |
Answer» D. 4 m | |
10. |
What is the speed limit on the national highway on hill road in Kmph? |
A. | 60 |
B. | 50 |
C. | 40 |
D. | 30 |
Answer» C. 40 | |
11. |
What is the strip length to be surveyed on the straight alignment? |
A. | 5 m |
B. | 10 m |
C. | 15 m |
D. | 30 m |
Answer» D. 30 m | |
12. |
The bench marks are fixed during the __________ |
A. | Preliminary survey |
B. | Reconnaissance |
C. | Detailed survey |
D. | After detailed project report |
Answer» D. After detailed project report | |
13. |
The general route for alignment is selected during __________ |
A. | Reconnaissance |
B. | Trace cut |
C. | Detailed survey |
D. | Detailed project report |
Answer» B. Trace cut | |
14. |
The alignment of hill roads is divided into how many stages? |
A. | One |
B. | Two |
C. | Three |
D. | Four |
Answer» D. Four | |