MCQOPTIONS
Saved Bookmarks
| 1. |
While scheduling a project by C.P.M. |
| A. | A project is divided into various activities |
| B. | Required time for each activity is established |
| C. | Net work is drawn by connecting the activities and the events |
| D. | All the above |
| Answer» E. | |