1.

While driving a large number of piles in loose sand :

A. It is advantageous to follow a sequence of pile driving such that the inner piles are driven first and then proceed outwards
B. It is advantageous to follow a sequence of pile driving such that the piles near the periphery are driven first and inner piles are driven later
C. It is advantageous to follow a sequence of pile driving such that alternately inner and outer piles are driven
D. Driving of piles can be done in any random order
Answer» B. It is advantageous to follow a sequence of pile driving such that the piles near the periphery are driven first and inner piles are driven later