| 1. |
Which of the following methods of offsets involves less measurement on the ground? |
| A. | ethod of perpendicular offsets |
| B. | ethod of oblique offsets |
| C. | ethod of ties |
| D. | ll involve equal measurement on the ground |
| Answer» B. ethod of oblique offsets | |