MCQOPTIONS
Saved Bookmarks
1. |
Which of the following is not part of the Measure activity in the DMAIC Model of Six Sigma? |
A. | Determining operational definitions |
B. | Establishing performance standards |
C. | Developing the project plan |
D. | Developing data collection and sample plan |
Answer» D. Developing data collection and sample plan | |