1.

Which contract type should be used by the owner on a high risk project?

A. Cost plus percentage of cost
B. Cost plus incentive fee
C. Lump sum
D. Fixed price plus incentive fee
Answer» D. Fixed price plus incentive fee


Discussion

No Comment Found